Sahla said:   4 years ago
100 * .04=4cu.m of wet concrete.

To produced 1cu.m of concrete 1.54cu.m of dry concrete required.

1.54 * 4 = 6.16cu.m
6.16/1+2+4 = .88 cu.m of cement reqd.
.88 * 1440 (density of cement)=1267.2 kg.

Or,
1267.2/50kg = 25.34=26 bag of cement.

Deepankar said:   4 years ago
The given answer is correct.

1st total volume=100 * 0.04 =4 m^3.
The volume is increased by 10% due to uneven surface which gives = 4 * 1.1 = 4.4 m^3.
This volume is further increased by 50% for dry volume calculation = 4.4 * 1.5 = 6.6 m^3.
So total volume = 6.6 m^3.
For cement = (6.6 * 1)/(1+2+4) = 0.9428 m^3.
(5)

Muhammad Tariq said:   4 years ago
The correct answer is 94.
Volume of wet concrete in 4cum.
Volume of dry concrete is=4*1.54( constant),
Total v= 6.61.
Quantity of cement = 1/7 * 6.61 = 0.94.
(1)

MJM Gcek said:   4 years ago
The correct answer is 0.88m3.

V C SAWATHKAR said:   4 years ago
For 4cm thick flooring constant of rate analysis is 6.6.
6.6/(1+2+4) = 0.94285,

for 2.5cm thick flooring 4.125.

MJM Gcek said:   4 years ago
The answer is 0.88m^3.
(1)

Noora S B said:   4 years ago
1.54 is the conversion factor to convert wet to dry mix and additional they take 10% for unevenness & loss. So, total 1.64.

Nasir waheed said:   4 years ago
0.88 m^3 is the right answer.

Ajay Sharma said:   4 years ago
(1/7) * 1.54 * 4 = 0.88m^3 = 0.9m^3.

Khld said:   4 years ago
. 88 m^3 is the right answer.