For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
0.90 m3
0.94 m3
0.98 m3
1.00 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
25 comments Page 3 of 3.

Khld said:   4 years ago
164.5 is assumed, how?

Asadullah mehsud said:   4 years ago
0.88cum.
Valume of dry cement concreat 100 * .04= 4cum,
Valume of wet concreat =4 * 1.54 = 6.16,
Valume of cement = 1/7 * 6.16 = 0.88cum.

Eng.RAJ said:   1 decade ago
Generally to calculate the Cement, fine aggregate and coarse aggregate the following method will be followed,



Wet Qty. of concrete = 100 Sqm * 0.04m thickness = 4.00 m^3

To get the dry volume of concrete, generally wet volume of concrete will be multiplied by 150%.



Therefore 4.00 m^3 * 150% = 6.00 m^3.



Cement Qty. = Dry volume of concrete / ( Sum of the ratio values).



= 6.00 /( 1+2+4).

= 0.857 m^3 of Cement i.e.25 No. of bags.



But here they considered 164.5% instead of 150%.



Dry volume of concrete = 4 * 164.5% = 6.58 m^3.



Cement Qty. = 6.58/ (1+2+4) = 0.94 m^3 of Cement i.e. 27.5 bags.

Ratul boruah said:   1 decade ago
How to calculate the Qty of cement?

Sonu said:   1 decade ago
Hi.



Please tell me, How to calculate the Qty of cement 0.940 m^3 ?