The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
1.00 m3
1.25 m3
1.50 m3
1.75 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
6 comments Page 1 of 1.

Suhas gotmare said:   7 years ago
Brickwork plinth 1.25m 3 per mason.

Superstructure 1m 3 per mason per day.

Kanti said:   6 years ago
According to me, it is .63 in (1:6) for brickwork in foundation and plinth.

Gunasekaran.m said:   4 years ago
Mud mortar is 1.25 m3.then how it is? Explain, please.
(1)

Sahil said:   7 years ago
How? please Explain.

Dan said:   7 years ago
How is it possible?

Bhupender said:   9 years ago
Yes, it is right.