Civil Engineering - Estimating and Costing - Discussion

Discussion Forum : Estimating and Costing - Section 1 (Q.No. 22)
22.
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
0.200 m3
0.247 m3
0.274 m3
0.295 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
43 comments Page 4 of 5.

Govind said:   6 years ago
Thanks everyone for explaining the solution.

Jon said:   5 years ago
Why take 30% extra here? Please explain me.

Aaina said:   9 years ago
If it's 15mm thick then what is the answer?

Philip Isabirye said:   3 years ago
Interesting, Thanks all for explaining.
(3)

Hari said:   5 years ago
Why we take 30% extra? Please explain.

Pritam said:   1 decade ago
How could you take, extra 30% morter?

Kaku said:   5 years ago
The correct answer is 0.2228m3.

SHOHEL said:   2 years ago
The Correct answer is 0.247 m3.
(1)

Deepak said:   7 years ago
Why to increase by its 30%?

Salma said:   8 years ago
1*100*. 012*1. 54/7 =. 274.