Discussion Forum : Estimating and Costing - Section 1 (Q.No. 22)
22.
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
0.200 m3
0.247 m3
0.274 m3
0.295 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
43 comments Page 5 of 5.

Basanta said:   3 years ago
It's for 0.247m3.
(2)

Adhiyaman said:   8 years ago
Thanks to all.

Bharat said:   6 years ago
Thanks all.