Discussion Forum : Estimating and Costing - Section 1 (Q.No. 22)
22.
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
0.200 m3
0.247 m3
0.274 m3
0.295 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
43 comments Page 4 of 5.

Adebola said:   9 years ago
I think answers may vary because one may decide to allow 10-20% for wastage& 30%-35% for shrinkage.

Brijesh vishwakarma said:   9 years ago
Volume of plaster = 0.012 * 100 = 1.2 m^3.

Add 60% for new wall depression & wastages volume of plaster = 1.2 + 1.2 * 60% = 1.92 cum.

Cement = 1.92 * 1/7 = 0.274 m^3.

Puja mandal said:   9 years ago
According to me, it is .012 * 100 = 1.2, dry wt = 1.54 * 1.2 = 1.848, 1.848 ÷ 7 = .264.

P Takhe Lomdak said:   1 decade ago
How it is calculated out please tell me the procedure?

Arjun said:   9 years ago
As per my solution, it's 33 percent extra why you are taking 30 percent?

Sufazo said:   8 years ago
According to this answer, they taking 60% extra => 1.2 * 60/100 = 0.274.

Shahanshah khan said:   8 years ago
I think dry value taken so large in solution maximum take extra 20% to 30%.

Mohit said:   8 years ago
If it is 15 mm thick than answer is .345 cum.

Adhiyaman said:   8 years ago
Thanks to all.

Salma said:   8 years ago
1*100*. 012*1. 54/7 =. 274.