Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 22)
22.
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
Discussion:
43 comments Page 4 of 5.
Adebola said:
9 years ago
I think answers may vary because one may decide to allow 10-20% for wastage& 30%-35% for shrinkage.
Brijesh vishwakarma said:
9 years ago
Volume of plaster = 0.012 * 100 = 1.2 m^3.
Add 60% for new wall depression & wastages volume of plaster = 1.2 + 1.2 * 60% = 1.92 cum.
Cement = 1.92 * 1/7 = 0.274 m^3.
Add 60% for new wall depression & wastages volume of plaster = 1.2 + 1.2 * 60% = 1.92 cum.
Cement = 1.92 * 1/7 = 0.274 m^3.
Puja mandal said:
9 years ago
According to me, it is .012 * 100 = 1.2, dry wt = 1.54 * 1.2 = 1.848, 1.848 ÷ 7 = .264.
P Takhe Lomdak said:
1 decade ago
How it is calculated out please tell me the procedure?
Arjun said:
9 years ago
As per my solution, it's 33 percent extra why you are taking 30 percent?
Sufazo said:
8 years ago
According to this answer, they taking 60% extra => 1.2 * 60/100 = 0.274.
Shahanshah khan said:
8 years ago
I think dry value taken so large in solution maximum take extra 20% to 30%.
Mohit said:
8 years ago
If it is 15 mm thick than answer is .345 cum.
Adhiyaman said:
8 years ago
Thanks to all.
Salma said:
8 years ago
1*100*. 012*1. 54/7 =. 274.
Post your comments here: