8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
500 m3
1000 m3
1500 m3
2000 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
42 comments Page 3 of 5.

VENKATESH AARE said:   10 years ago
Total volume = L*B*D. So 1000*8*(25/100) = 2000 cum.

Ravi s murnal said:   8 years ago
@Usman.

Explain 6.25 compaction. How you get it?

Rakhi Alwin said:   9 years ago
What does this box cutting mean? Explain it.

Rahul said:   9 years ago
@Usman.

Hou you define 6.25 is compacted?

Sonali said:   7 years ago
I think the answer is 2000m3 is correct.

Saket said:   1 decade ago
What is the box cutting in road crust?

Amit said:   8 years ago
I don't understand it. Please explain.

ANANDA MARNDI said:   6 years ago
How to solve this? Please explain me.

Burhan said:   7 years ago
@Rishabh.

Why you divide 2000 by 4?

Vishal said:   5 years ago
1000*8*0.15 = 1200;m3.