Discussion Forum : Estimating and Costing - Section 2 (Q.No. 8)
8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
Discussion:
42 comments Page 3 of 5.
VENKATESH AARE said:
10 years ago
Total volume = L*B*D. So 1000*8*(25/100) = 2000 cum.
Ravi s murnal said:
8 years ago
@Usman.
Explain 6.25 compaction. How you get it?
Explain 6.25 compaction. How you get it?
Rakhi Alwin said:
9 years ago
What does this box cutting mean? Explain it.
Rahul said:
9 years ago
@Usman.
Hou you define 6.25 is compacted?
Hou you define 6.25 is compacted?
Sonali said:
7 years ago
I think the answer is 2000m3 is correct.
Saket said:
1 decade ago
What is the box cutting in road crust?
Amit said:
8 years ago
I don't understand it. Please explain.
ANANDA MARNDI said:
6 years ago
How to solve this? Please explain me.
Burhan said:
7 years ago
@Rishabh.
Why you divide 2000 by 4?
Why you divide 2000 by 4?
Vishal said:
5 years ago
1000*8*0.15 = 1200;m3.
SSC je 2016.
SSC je 2016.
(2)