Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 2 (Q.No. 8)
8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
Discussion:
42 comments Page 1 of 5.
Takhe Lomdak said:
1 decade ago
How to calculate this problem?
Saket said:
1 decade ago
What is the box cutting in road crust?
Habib Mansuri said:
1 decade ago
I want explanation answer.
Shivansh sharma said:
1 decade ago
According to me 1000*8*0.15-1200 over sub base.
1000*8*0.10-800 for gravel. Total-2000 cum.
1000*8*0.10-800 for gravel. Total-2000 cum.
VENKATESH AARE said:
10 years ago
Total volume = L*B*D. So 1000*8*(25/100) = 2000 cum.
SHAMPA SADHUKHAN said:
9 years ago
How to solve the problem?
Give explanation in step by step.
Give explanation in step by step.
Rakhi Alwin said:
9 years ago
What does this box cutting mean? Explain it.
Usman said:
9 years ago
The road is 1000m long = 1000m.
The width is 8m = 8m.
The thickness of slab = 0.15m.
Excavation for sub base (10cm thick - 6.25cm compaction) = 3.75cm for gravel.
So,
1000m x 8m x (0.15m + .0375m).
1000m x 8m x 0.1875m = 1500 cubic m.
The width is 8m = 8m.
The thickness of slab = 0.15m.
Excavation for sub base (10cm thick - 6.25cm compaction) = 3.75cm for gravel.
So,
1000m x 8m x (0.15m + .0375m).
1000m x 8m x 0.1875m = 1500 cubic m.
(1)
Rahul said:
9 years ago
@Usman.
Hou you define 6.25 is compacted?
Hou you define 6.25 is compacted?
Adebola said:
9 years ago
How do you define the 6.25 compaction & the remaining part of the calculation?
Post your comments here: