Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 2 (Q.No. 8)
8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
Discussion:
42 comments Page 2 of 5.
Pratap said:
9 years ago
Please explain in detail.
MITHUN said:
8 years ago
Not getting this, please explain.
Amit said:
8 years ago
I don't understand it. Please explain.
Amit said:
8 years ago
What is 6.25? Please explain.
Ravi s murnal said:
8 years ago
@Usman.
Explain 6.25 compaction. How you get it?
Explain 6.25 compaction. How you get it?
Madhu said:
8 years ago
Where did the 10cm thick gravel? and how would you know that 6.25compaction? totally confusing. Please explain this.
Deeptikant sharma said:
8 years ago
15/4 = 3.75 then,
10cm - compaction 3.75 = 6.25 cm.
10cm - compaction 3.75 = 6.25 cm.
(1)
Bhavna said:
8 years ago
Please solve this in detail.
Vikas kumar said:
8 years ago
2000 Cum is the correct answer.
(1)
Ziauddin said:
8 years ago
@Deeptikant Sharma.
What is 15/4?
What is 15/4?