Civil Engineering - Estimating and Costing - Discussion

Discussion Forum : Estimating and Costing - Section 2 (Q.No. 8)
8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
500 m3
1000 m3
1500 m3
2000 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
42 comments Page 2 of 5.

Pratap said:   9 years ago
Please explain in detail.

MITHUN said:   8 years ago
Not getting this, please explain.

Amit said:   8 years ago
I don't understand it. Please explain.

Amit said:   8 years ago
What is 6.25? Please explain.

Ravi s murnal said:   8 years ago
@Usman.

Explain 6.25 compaction. How you get it?

Madhu said:   8 years ago
Where did the 10cm thick gravel? and how would you know that 6.25compaction? totally confusing. Please explain this.

Deeptikant sharma said:   8 years ago
15/4 = 3.75 then,

10cm - compaction 3.75 = 6.25 cm.
(1)

Bhavna said:   8 years ago
Please solve this in detail.

Vikas kumar said:   8 years ago
2000 Cum is the correct answer.
(1)

Ziauddin said:   8 years ago
@Deeptikant Sharma.

What is 15/4?