8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
500 m3
1000 m3
1500 m3
2000 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
42 comments Page 2 of 5.

Madhu said:   8 years ago
Where did the 10cm thick gravel? and how would you know that 6.25compaction? totally confusing. Please explain this.

Akash Singh said:   5 years ago
Original volume= 1000*8*(15+10) = 2000m3.
Cut off volume= 1/4 * 2000 = 500m3.
Box cutting=2000-500= 1500m3.
(1)

Swati said:   6 years ago
Box cutting = lbh of concrete + lbh gravel.
=1000 * 8 * 0.15 + 1000 * 8 * 0.10,
= 1200 + 800,
= 2000.
(3)

Shivansh sharma said:   1 decade ago
According to me 1000*8*0.15-1200 over sub base.

1000*8*0.10-800 for gravel. Total-2000 cum.

Ranjith said:   4 years ago
L = 1000m,
B = 8.00m,
D = (0.15m+0.10m),
Q = LXBXD = 1000m X 8.00mX 0.25m = 2000 cu.m.
(4)

Adebola said:   9 years ago
How do you define the 6.25 compaction & the remaining part of the calculation?

Dalwinder singh said:   5 years ago
1000 * 8 * 0.15= 1200.
1000 * 8 * 0.10 = 800.
1200 + 800 = 2000m3.
(3)

Bipin said:   7 years ago
Box cutting in road crust= 1000 * 8 * (0.15+0.10).
= 2000m^3.

SHAMPA SADHUKHAN said:   9 years ago
How to solve the problem?
Give explanation in step by step.

Deeptikant sharma said:   8 years ago
15/4 = 3.75 then,

10cm - compaction 3.75 = 6.25 cm.
(1)