8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
Discussion:
42 comments Page 3 of 5.
Bharath said:
8 years ago
6.25 cm fixed ah?
Aamir said:
8 years ago
Box cutting means to the excavation of the road so as to fit the road in the excavated portion this is done to make road level with the surrounding, now you have remembered that there is compaction of 6.25cm in gravel in the subbase so remaining total available ht will be 15+3.75cm, and then as usual l*b*h.
Ziauddin said:
8 years ago
@Deeptikant Sharma.
What is 15/4?
What is 15/4?
Vikas kumar said:
8 years ago
2000 Cum is the correct answer.
(1)
Bhavna said:
8 years ago
Please solve this in detail.
Deeptikant sharma said:
8 years ago
15/4 = 3.75 then,
10cm - compaction 3.75 = 6.25 cm.
10cm - compaction 3.75 = 6.25 cm.
(1)
Madhu said:
8 years ago
Where did the 10cm thick gravel? and how would you know that 6.25compaction? totally confusing. Please explain this.
Ravi s murnal said:
8 years ago
@Usman.
Explain 6.25 compaction. How you get it?
Explain 6.25 compaction. How you get it?
Amit said:
8 years ago
What is 6.25? Please explain.
Amit said:
8 years ago
I don't understand it. Please explain.
Post your comments here: