Civil Engineering - Estimating and Costing - Discussion

Discussion Forum : Estimating and Costing - Section 2 (Q.No. 8)
8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
500 m3
1000 m3
1500 m3
2000 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
42 comments Page 4 of 5.

MITHUN said:   8 years ago
Not getting this, please explain.

Pratap said:   9 years ago
Please explain in detail.

Adebola said:   9 years ago
How do you define the 6.25 compaction & the remaining part of the calculation?

Rahul said:   9 years ago
@Usman.

Hou you define 6.25 is compacted?

Usman said:   9 years ago
The road is 1000m long = 1000m.
The width is 8m = 8m.
The thickness of slab = 0.15m.
Excavation for sub base (10cm thick - 6.25cm compaction) = 3.75cm for gravel.

So,
1000m x 8m x (0.15m + .0375m).
1000m x 8m x 0.1875m = 1500 cubic m.
(1)

Rakhi Alwin said:   9 years ago
What does this box cutting mean? Explain it.

SHAMPA SADHUKHAN said:   9 years ago
How to solve the problem?
Give explanation in step by step.

VENKATESH AARE said:   10 years ago
Total volume = L*B*D. So 1000*8*(25/100) = 2000 cum.

Shivansh sharma said:   1 decade ago
According to me 1000*8*0.15-1200 over sub base.

1000*8*0.10-800 for gravel. Total-2000 cum.

Habib Mansuri said:   1 decade ago
I want explanation answer.