40.
The time which results in the least, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
26 comments Page 1 of 3.

Avinash said:   8 years ago
What is meant by leasi?

Rahul said:   8 years ago
I think it is least.

Sanjeev rai said:   8 years ago
The answer should be a normal time.

Narayan adhikari said:   8 years ago
The answer should be normal time.

Uttam Baral said:   8 years ago
Yeah, it's should be A.

Avinash said:   8 years ago
Yeah, definitely it's normal time.

Aditya said:   8 years ago
Std time for completing an activity is normal time and least time required is the crash time.

Roy said:   8 years ago
Yes, it's crash time.

Pramod yadav said:   7 years ago
Crash time is the least time for construction. So it's B.

Bharat said:   7 years ago
For least cost time is slow,

For normal cost, it is Normal time.