Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 40)
40.
The time which results in the least, possible construction cost of an activity, is known
Discussion:
26 comments Page 1 of 3.
Shafqat said:
2 years ago
Slow time means Increase in Labour Cost.
Crash time also increase the Labour Cost.
Answer should be Standard or Normal time from these options.
Crash time also increase the Labour Cost.
Answer should be Standard or Normal time from these options.
Umair Ahmad said:
4 years ago
A least-cost schedule is one with optimum project duration such that to lengthen or shorten it would Increase the project total cost.
Durgesh Prashad said:
4 years ago
As per graph between Direct Cost and Time, the Normal time is the least time corresponding to Normal Cost which is again minimum.
Subha prakash Sahoo said:
4 years ago
There is no any concept of a slow time for normal time cost is normal cost least cost occurs at the optimum time only.
Ajay said:
6 years ago
In this question, mention that least possible construction cost of an activity so that would be answer Normal time.
Ashu said:
7 years ago
Crash time is min time in which we employ extra resources so it's cost increases.
Hence normal duration is answer.
Hence normal duration is answer.
Kishan said:
6 years ago
Options are wrong correct answer is optimum time which lies between crash time and normal time.
Aditya said:
8 years ago
Std time for completing an activity is normal time and least time required is the crash time.
Saroj said:
6 years ago
If we slow activities cash flow is minimal so B could be right answer.
Beroj gar said:
6 years ago
Optimum duration means standard time.
So, the correct Answer is D.
So, the correct Answer is D.
Post your comments here: