Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 40)
40.
The time which results in the least, possible construction cost of an activity, is known
Discussion:
26 comments Page 1 of 3.
Shafqat said:
2 years ago
Slow time means Increase in Labour Cost.
Crash time also increase the Labour Cost.
Answer should be Standard or Normal time from these options.
Crash time also increase the Labour Cost.
Answer should be Standard or Normal time from these options.
D prasad said:
3 years ago
Yes, it should be a normal time.
(2)
Prabin.. said:
3 years ago
Slow time = optimum time.
Subha prakash Sahoo said:
4 years ago
There is no any concept of a slow time for normal time cost is normal cost least cost occurs at the optimum time only.
MJM Gcek said:
4 years ago
Agreed @Kishan.
Umair Ahmad said:
4 years ago
A least-cost schedule is one with optimum project duration such that to lengthen or shorten it would Increase the project total cost.
Durgesh Prashad said:
4 years ago
As per graph between Direct Cost and Time, the Normal time is the least time corresponding to Normal Cost which is again minimum.
Dev said:
5 years ago
I tgink it should be optimum time.
Dipunku said:
5 years ago
Crash time because it shows some possibilities to reduce cost.
Kishan said:
6 years ago
Options are wrong correct answer is optimum time which lies between crash time and normal time.