The time which results in the least, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
26 comments Page 3 of 3.

Prabin.. said:   3 years ago
Slow time = optimum time.

Avinash said:   8 years ago
What is meant by leasi?

Uttam Baral said:   8 years ago
Yeah, it's should be A.

Roy said:   8 years ago
Yes, it's crash time.

Rahul said:   8 years ago
I think it is least.

MJM Gcek said:   4 years ago
Agreed @Kishan.