Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 40)
40.
The time which results in the least, possible construction cost of an activity, is known
Discussion:
26 comments Page 3 of 3.
Umair Ahmad said:
4 years ago
A least-cost schedule is one with optimum project duration such that to lengthen or shorten it would Increase the project total cost.
MJM Gcek said:
4 years ago
Agreed @Kishan.
Subha prakash Sahoo said:
4 years ago
There is no any concept of a slow time for normal time cost is normal cost least cost occurs at the optimum time only.
Prabin.. said:
3 years ago
Slow time = optimum time.
D prasad said:
3 years ago
Yes, it should be a normal time.
(2)
Shafqat said:
2 years ago
Slow time means Increase in Labour Cost.
Crash time also increase the Labour Cost.
Answer should be Standard or Normal time from these options.
Crash time also increase the Labour Cost.
Answer should be Standard or Normal time from these options.
Post your comments here: