40.
The time which results in the least, possible construction cost of an activity, is known
Discussion:
26 comments Page 2 of 3.
Rahul said:
7 years ago
It's should be a normal time.
Ashu said:
7 years ago
Crash time is min time in which we employ extra resources so it's cost increases.
Hence normal duration is answer.
Hence normal duration is answer.
Saork said:
6 years ago
Answer is optimum duration/time but not given in option.
Beroj gar said:
6 years ago
Optimum duration means standard time.
So, the correct Answer is D.
So, the correct Answer is D.
Saroj said:
6 years ago
If we slow activities cash flow is minimal so B could be right answer.
Ajay said:
6 years ago
In this question, mention that least possible construction cost of an activity so that would be answer Normal time.
Kishan said:
6 years ago
Options are wrong correct answer is optimum time which lies between crash time and normal time.
Dipunku said:
5 years ago
Crash time because it shows some possibilities to reduce cost.
Dev said:
5 years ago
I tgink it should be optimum time.
Durgesh Prashad said:
4 years ago
As per graph between Direct Cost and Time, the Normal time is the least time corresponding to Normal Cost which is again minimum.