Discussion Forum : Construction Management - Section 1 (Q.No. 40)
40.
The time which results in the least, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
26 comments Page 2 of 3.

Rahul said:   7 years ago
It's should be a normal time.

Ashu said:   7 years ago
Crash time is min time in which we employ extra resources so it's cost increases.

Hence normal duration is answer.

Saork said:   6 years ago
Answer is optimum duration/time but not given in option.

Beroj gar said:   6 years ago
Optimum duration means standard time.

So, the correct Answer is D.

Saroj said:   6 years ago
If we slow activities cash flow is minimal so B could be right answer.

Ajay said:   6 years ago
In this question, mention that least possible construction cost of an activity so that would be answer Normal time.

Kishan said:   6 years ago
Options are wrong correct answer is optimum time which lies between crash time and normal time.

Dipunku said:   5 years ago
Crash time because it shows some possibilities to reduce cost.

Dev said:   5 years ago
I tgink it should be optimum time.

Durgesh Prashad said:   4 years ago
As per graph between Direct Cost and Time, the Normal time is the least time corresponding to Normal Cost which is again minimum.


Post your comments here: