Civil Engineering - Estimating and Costing - Discussion

Discussion Forum : Estimating and Costing - Section 1 (Q.No. 1)
1.
Pick up the excavation where measurements are made in square metres for payment.
Ordinary cuttings up to 1 m
surface dressing up to 15 cm depths
Surface excavation up to 30 cm depths
Both (b) and (c)
Both (a) and (b)
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
22 comments Page 1 of 3.

Vaxoo said:   3 years ago
Surface dressing is by default measured in m2.

For excavation of width>1.5m and depth<30cm measured in m2.
(2)

Arjun acharya said:   4 years ago
I think option 1 is also right.

Kishan said:   5 years ago
Excavation up to 30 cm measured in sqm.

Excavation more than 30cm measured in cubic m.
(1)

Shalini said:   6 years ago
Yes, right. Thanks @Maqbool.

Mithun said:   6 years ago
Thanks @Gowher.

Rabindra said:   7 years ago
Thanks @Satish.

Gowher maqbool said:   7 years ago
Excavation exceeding 1.5 m in width, as well as IO m^2 on plan but not exceeding 300 mm in depth, shall be described as 'surface excavation' and measured in square metres.

Trimming of ground surface to remove small inequalities not exceeding I50 mm deep shall be described as surface dressing and measured in square metres.
(3)

Er muqeem said:   7 years ago
How to measure place in square meter?
(1)

Mahesh shalivahana said:   8 years ago
Thanks @Satish.

DASHARATH PATEL said:   8 years ago
No, the excavations are measure in cubic metre.


Post your comments here:

Your comments will be displayed after verification.