Discussion Forum : Construction Management - Section 1 (Q.No. 40)
40.
The time which results in the least, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
26 comments Page 3 of 3.

Aditya said:   8 years ago
Std time for completing an activity is normal time and least time required is the crash time.

Avinash said:   8 years ago
Yeah, definitely it's normal time.

Uttam Baral said:   8 years ago
Yeah, it's should be A.

Narayan adhikari said:   8 years ago
The answer should be normal time.

Sanjeev rai said:   8 years ago
The answer should be a normal time.

Rahul said:   8 years ago
I think it is least.