40.
The time which results in the least, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
26 comments Page 2 of 3.

Kishan said:   6 years ago
Options are wrong correct answer is optimum time which lies between crash time and normal time.

Ajay said:   6 years ago
In this question, mention that least possible construction cost of an activity so that would be answer Normal time.

Saroj said:   6 years ago
If we slow activities cash flow is minimal so B could be right answer.

Avinash said:   8 years ago
What is meant by leasi?

Saork said:   6 years ago
Answer is optimum duration/time but not given in option.

Ashu said:   7 years ago
Crash time is min time in which we employ extra resources so it's cost increases.

Hence normal duration is answer.

Rahul said:   7 years ago
It's should be a normal time.

Bharat said:   7 years ago
For least cost time is slow,

For normal cost, it is Normal time.

Pramod yadav said:   7 years ago
Crash time is the least time for construction. So it's B.

Roy said:   8 years ago
Yes, it's crash time.