Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 2 (Q.No. 18)
18.
For completion of a project, the critical path of the network represents
minimum time
maximum time
maximum cost
minimum cost.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
40 comments Page 3 of 4.

Lokesh aggarwal said:   6 years ago
Critical path shows the maximum time so that all the activities have sufficeint time to be completed.

Abdul Muttalib baloch said:   6 years ago
Critical path is the longest and consumes maximum resources and minimum time.

Vrushik said:   1 decade ago
How? I think the answer is B. As the total time in critical path is maximum.

Utsav said:   7 years ago
B is correct.

Other routes may be short but won't complete the work.

Prateek bansal said:   9 years ago
CPM is based on cost optimisation, so the answer may be minimum cost.

Navin said:   1 decade ago
Correct answer option B, because critical path is the longest path.

Rajashekhar Hallur said:   9 years ago
Yes, its maximum duration of activities and hence its maximum time.

PAWAN said:   6 years ago
The right option is A. Because no time for delay in critical path.

Naveen said:   6 years ago
Answer will be B time taken along critical path is always maximum.

Baloch said:   9 years ago
CP consumes maximum resources and time.

Hence it's longest.