For completion of a project, the critical path of the network represents
Discussion:
40 comments Page 1 of 4.
Engr khan said:
3 years ago
The critical path will be the longest path in the network requiring the maximum amount of time, but it will represent the minimum duration that is required to complete all the activities i.e. completion of a project.
(9)
Ashutosh said:
4 years ago
Answer a is correct. Because critical time wise the longest path but it has minimum duration to complete the whole project.
(3)
Deepak aryal said:
5 years ago
Minumum time and longest path is the correct answer because we have to choose the longest path so that we can finish in minimum time. This may sound odd but this is the real answer.
(2)
Bhavish said:
5 years ago
The critical path is the longest path time-wise, is true. But the question is.
'For completion of a project' so the answer is option A. Because no matter how many resources you put in, you cannot complete the project within the critical path. The critical path is the MINIMUM time in which you can complete the project along the longest path.
'For completion of a project' so the answer is option A. Because no matter how many resources you put in, you cannot complete the project within the critical path. The critical path is the MINIMUM time in which you can complete the project along the longest path.
(2)
Ajay Kumar Yadav said:
3 years ago
A is the correct answer.
The critical path provides the minimum time required to complete the project. And it provides max. Time among different paths. So option A is correct.
The critical path provides the minimum time required to complete the project. And it provides max. Time among different paths. So option A is correct.
(1)
Subha prakash Sahoo said:
4 years ago
Critical path is the network of critical activities and less than the critical time the Project can't be completed and without critical activities project can't be completed thus in a network Critical path is the longest path but it indicates Minm time to complete a project.
(1)
Lokesh aggarwal said:
6 years ago
Critical path shows the maximum time so that all the activities have sufficeint time to be completed.
Himal said:
7 years ago
The right Option is A.
Naveen said:
6 years ago
Answer will be B time taken along critical path is always maximum.
PAWAN said:
6 years ago
The right option is A. Because no time for delay in critical path.