Discussion Forum : Concrete Technology - Section 2 (Q.No. 44)
44.
If the depth of moist sand in a cylinder is 15 cm and the depth of the sand when fully inundated with water is 12 cm, the bulking of the moist sand, is
Discussion:
14 comments Page 2 of 2.
Prashant jadhav said:
1 decade ago
Formula = ((h-h1)/h1)*100.
= 25%.
= 25%.
Nitin said:
1 decade ago
15-12/15*100 shall comes 20 %, so the option should be D.
Kamran said:
10 years ago
Thanks to all improving our knowledge.
WASEEM SANGI said:
3 years ago
We can solve it simply as;
Dry volume and inundated volume are equal so the original volume of sand is 12 cm
12cm = 100% volume of given sample.
3cm = 100/4 = 25cm.
The sand bulks by 3cm and depth become 15cm which is 3cm greater than the original depth so bulking of sand is 3cm or 25%.
Dry volume and inundated volume are equal so the original volume of sand is 12 cm
12cm = 100% volume of given sample.
3cm = 100/4 = 25cm.
The sand bulks by 3cm and depth become 15cm which is 3cm greater than the original depth so bulking of sand is 3cm or 25%.
Post your comments here: