Civil Engineering - Concrete Technology

Why should I learn to solve Civil Engineering questions and answers section on "Concrete Technology"?

Learn and practise solving Civil Engineering questions and answers section on "Concrete Technology" to enhance your skills so that you can clear interviews, competitive examinations, and various entrance tests (CAT, GATE, GRE, MAT, bank exams, railway exams, etc.) with full confidence.

Where can I get the Civil Engineering questions and answers section on "Concrete Technology"?

IndiaBIX provides you with numerous Civil Engineering questions and answers based on "Concrete Technology" along with fully solved examples and detailed explanations that will be easy to understand.

Where can I get the Civil Engineering section on "Concrete Technology" MCQ-type interview questions and answers (objective type, multiple choice)?

Here you can find multiple-choice Civil Engineering questions and answers based on "Concrete Technology" for your placement interviews and competitive exams. Objective-type and true-or-false-type questions are given too.

How do I download the Civil Engineering questions and answers section on "Concrete Technology" in PDF format?

You can download the Civil Engineering quiz questions and answers section on "Concrete Technology" as PDF files or eBooks.

How do I solve Civil Engineering quiz problems based on "Concrete Technology"?

You can easily solve Civil Engineering quiz problems based on "Concrete Technology" by practising the given exercises, including shortcuts and tricks.

1.
For quality control of Portland cement, the test essentially done is
setting time
soundness
tensile strength
consistency
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

2.
If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the percentage of water is,
20%
25%
30%
35%
40%
Answer: Option
Explanation:
No answer description is available. Let's discuss.

3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
7 days for beam soffits
14 days for bottom slabs of spans 4.6 m and more
21 days for bottom beams over 6 m spans
2 days for vertical sides of columns
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

4.
Wp and Wf are the weights of a cylinder containing partially compacted and fully compacted concrete. If the compaction factor is 0.95, the workability of concrete is
extremely low
very low
low
high
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

5.
For given water content, workability decreases if the concrete aggregates contain an excess of
thin particles
flat particles
elongated particles
flaky paticles
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.