A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
281 comments Page 3 of 29.

Jagadish Behera said:   3 years ago
"A" is 3 times more than" B" (efficiency)

Difference = 60 days

3x-x = 60

X = 30days This is" B"

A=3 * 30 = 90 days.

So Total work =180

A=2 WORK
B=6 WORK

A+B TOGETHER CAN DO IN 180/8 = 22.5 DAYS.
(14)

Gogo said:   3 years ago
A+B = (1/30 + 1/90) = 2/45.

How we are getting this?
(8)

HARINI said:   3 years ago
Given;

A = 3B;
A = B - 60.

Substitute A = 3B in 2nd equation(a=b-60).
3B = B-60
B = 30.

Therefore; A = 3B = 90.

A+B = (1/30 + 1/90) = 2/45.
So, the answer is 22(1/2).
(24)

Muhammad said:   4 years ago
Let A's total work completion time be = n.
B's total work completion time = 3n,
Difference between B and A's daily work = 60.
3n - n = 60,
2n = 60.
n = 30.

Total daily work.
=1/3n + 1/n,
=1/90 + 1/30,
=2/45,
So total time to complete for both = 45/2 = 22.5.
(12)

Jeeva said:   4 years ago
a ------ b
x ------ 3x.

1/3 of the work is remaining = 1 - 1/3.
= 2/3.

2/3 of the work is completed by b = 60 days.
one of the work is completed by b = 60 * 3/2.
b = 90.
B one day work = 1/90.
A one-day work = 1/30.
a+b = 1/30 + 1/90.
a+b = 4/90
a+b = 2/45.

A and B together can do the work = 45/2.
(1)

Sachin said:   4 years ago
Thanks everyone.
(1)

Padma said:   4 years ago
Here a simple calculation is;
A takes 1 part and B takes 3 parts.
\
So A:B ratio is 1:3.
total 4p.and the difference is 2,they did work in 60 days so 60p.
4p=60.
p=15/1.
B total working days 15*3=45.
W/t is 45/2.
(4)

Srikanth said:   4 years ago
Thanks @Sundhar.

Astik Mandal said:   4 years ago
A - 30d.
B - 90d.
lcm - 90(total work).
Efficiency of A - 3.
Efficiency of B - 1.

Total Efficiency = 4 total.

work/totalEfficiency=90/4=22.5.
(4)

HMJ said:   4 years ago
A=3B,
A can finish the job 60 days less then B,
Say, work=60.

Capacity of B = (60/x) ----> 1
Cap of A = (60/x-60) ----> 2.

As per the condition A=3B.

Compare the above equation by putting the Capacity of A = 3 times Capacity of B.

You will get x=90.
Now put this x in above equations 1 and 2.
You will get the cap of A = 2 and Cap of B = 0.66.

Working together,
Days= Work/(cap of A + cap of B).
= 60/2.66,
= 22.5.