Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
2 |
So, A takes 30 days to do the work.
A's 1 day's work = | 1 |
30 |
B's 1 day's work = | 1 |
90 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
30 | 90 | 90 | 45 |
![]() |
45 | = 22 | 1 | days. |
2 | 2 |
Discussion:
281 comments Page 1 of 29.
Sundar said:
1 decade ago
@All (Must read if you have any doubts)
If B takes 3 days then A takes 1 day to complete the task.
Time taken Ratio => A : B = 1 day : 3 days.
1 3 (difference is 2)
10 30 (diff 20)
30 90 (diff 60) <= Here diff is 60 days, So this is the correct ratio to be used in calculation, since it was mentioned in the given question.
A alone can finish the task in 30 days.
B alone can finish the task in 90 days.
Work done by A alone in 1 day = 1/30
Work done by B alone in 1 day = 1/90
Work done by A and B in one day (1/30 + 1/90) = 3+1/90 = 4/90
The no. of days required to complete the task by A and B is
= 90/4
= 22.5 days.
////**** Important Note: ****////
We cannot take other ratios like 1:3, 10:30, 40:120, 60:180 for the calculation. Since the diff is mentioned as 60 days.
Because, it will give different answers for each different ratios used for calculation.
If we take 1:3 => (1/1 + 1/3) = 4/3
If we take 10:30 => (1/10 + 1/30) = 4/30
If we take 40:120 = (1/40 + 1/120) = 4/120
If we take 60:180 => (1/60 + 1/180) = 4/180 ... so on.
I hope this will help you. Have a nice day!
If B takes 3 days then A takes 1 day to complete the task.
Time taken Ratio => A : B = 1 day : 3 days.
1 3 (difference is 2)
10 30 (diff 20)
30 90 (diff 60) <= Here diff is 60 days, So this is the correct ratio to be used in calculation, since it was mentioned in the given question.
A alone can finish the task in 30 days.
B alone can finish the task in 90 days.
Work done by A alone in 1 day = 1/30
Work done by B alone in 1 day = 1/90
Work done by A and B in one day (1/30 + 1/90) = 3+1/90 = 4/90
The no. of days required to complete the task by A and B is
= 90/4
= 22.5 days.
////**** Important Note: ****////
We cannot take other ratios like 1:3, 10:30, 40:120, 60:180 for the calculation. Since the diff is mentioned as 60 days.
Because, it will give different answers for each different ratios used for calculation.
If we take 1:3 => (1/1 + 1/3) = 4/3
If we take 10:30 => (1/10 + 1/30) = 4/30
If we take 40:120 = (1/40 + 1/120) = 4/120
If we take 60:180 => (1/60 + 1/180) = 4/180 ... so on.
I hope this will help you. Have a nice day!
(2)
Parveez said:
7 years ago
A is thrice as good as workman as B so the ratio of time taken by A and B is = 1:3.
Let, A completed the work in x days.
B completed the work in 3x days.
A's 1-day work= 1/x and B's 1-day work= 1/3x,
So, A+B 's 1-day work= 1/x+1/3x,
=4/3x.
So, A+B completed the work in 3x/4 days.
Since,
A finishes a job in 60 days less than B.
therefore , 3x-x=60.
x=30.
therefore, Working together A+B completed the work in 3x/4 days.
= 3*30/4.
= 45/2.
= 22 1/2 days.
Let, A completed the work in x days.
B completed the work in 3x days.
A's 1-day work= 1/x and B's 1-day work= 1/3x,
So, A+B 's 1-day work= 1/x+1/3x,
=4/3x.
So, A+B completed the work in 3x/4 days.
Since,
A finishes a job in 60 days less than B.
therefore , 3x-x=60.
x=30.
therefore, Working together A+B completed the work in 3x/4 days.
= 3*30/4.
= 45/2.
= 22 1/2 days.
(1)
Siva said:
1 decade ago
Hi Guys,
I think following simple method (alternate) will make you more clear,
A can complete work in N days => A's 1day work = (1/N)----1
B can complete work in n days => B's 1day work = (1/n)----2
Given data,
A thrice as B so , A=3B
A complete work 60 days less than B so, (N=n-60)
Apply in 1 & 2
A's 1day work = (1/(n-60))-----3
B's 1day work = (1/n)--------4
we know that A=3B ; B=(1/n) so,Apply B in A we get[A=3/n]
Apply in 3
3/n=(1/(n-60))
by solving,
3n-180=n
n=90
so, B can complete work in 90 Days => B's 1 Day work =(1/90)
we know that N=n-60,
so, A can complete work in 30 Days => A's 1 Day work = (1/30)
(A+B) 1 Day work = (1/30 + 1/90)
by solving we get,
A+B 1 Day work = 2/45,
so A and B together can complete work in 45/2 Days.
I think following simple method (alternate) will make you more clear,
A can complete work in N days => A's 1day work = (1/N)----1
B can complete work in n days => B's 1day work = (1/n)----2
Given data,
A thrice as B so , A=3B
A complete work 60 days less than B so, (N=n-60)
Apply in 1 & 2
A's 1day work = (1/(n-60))-----3
B's 1day work = (1/n)--------4
we know that A=3B ; B=(1/n) so,Apply B in A we get[A=3/n]
Apply in 3
3/n=(1/(n-60))
by solving,
3n-180=n
n=90
so, B can complete work in 90 Days => B's 1 Day work =(1/90)
we know that N=n-60,
so, A can complete work in 30 Days => A's 1 Day work = (1/30)
(A+B) 1 Day work = (1/30 + 1/90)
by solving we get,
A+B 1 Day work = 2/45,
so A and B together can complete work in 45/2 Days.
(1)
Sravan said:
10 years ago
Since it's mentioned that A completed 60 days less than B.
We have to know there less than rate. Since it given A is thrice as good as B.
That means it takes 1 day to A to do Bs 3 day work.
So now we can know that A can do in (3-1) = 2 days less than B.
That means A less than days for B days for 2 its 3.
Similarly for 60 less day we need to multiply 2 by 30 to get 60. Since we do on 2 (A) side we have to multiply on 3 (B) side then we get.
= 2x30 : 3x30.
We get = 60 (for A day's lesser than B) : 90 (we got B days) that means A work days = 90-60 = 30.
So 1/30 + 1/90= 0.0444 amount of work per 1 day.
For 1 piece of complete work 0.4444/0.4444 = 1/0.4444 days.
That 1 piece of work done for 22.5 days by A & B together.
We have to know there less than rate. Since it given A is thrice as good as B.
That means it takes 1 day to A to do Bs 3 day work.
So now we can know that A can do in (3-1) = 2 days less than B.
That means A less than days for B days for 2 its 3.
Similarly for 60 less day we need to multiply 2 by 30 to get 60. Since we do on 2 (A) side we have to multiply on 3 (B) side then we get.
= 2x30 : 3x30.
We get = 60 (for A day's lesser than B) : 90 (we got B days) that means A work days = 90-60 = 30.
So 1/30 + 1/90= 0.0444 amount of work per 1 day.
For 1 piece of complete work 0.4444/0.4444 = 1/0.4444 days.
That 1 piece of work done for 22.5 days by A & B together.
Shivaram vollala said:
1 decade ago
In the given question the ration of capacity of work in day a:b is = 3:1.
So always inverse proportion to capacity and work like the way a and b can do the work ration =1:3 i.e. a's one day work = b's three days work.
So let now finish work together is imagine x.
Ratios of each person a's work = x* 1/4 = X/4. (1).
Ration of b's work = x* 3/4 = 3X/4. (2).
In the given question difference is 60 days.
So 3X/4-X/4 = 60 Days.
Solove ther x we get x = 120.
Now substitute x in (1) and (2).
W e get a's part of one day work = 30 days.
And b's part of one day work = 90 days.
Now solve the.
A and B together work = 1/30+1/90 = 4/90 =2/45.
This is and b together part of work now one day work = 45/2 = 22.5 days.
So always inverse proportion to capacity and work like the way a and b can do the work ration =1:3 i.e. a's one day work = b's three days work.
So let now finish work together is imagine x.
Ratios of each person a's work = x* 1/4 = X/4. (1).
Ration of b's work = x* 3/4 = 3X/4. (2).
In the given question difference is 60 days.
So 3X/4-X/4 = 60 Days.
Solove ther x we get x = 120.
Now substitute x in (1) and (2).
W e get a's part of one day work = 30 days.
And b's part of one day work = 90 days.
Now solve the.
A and B together work = 1/30+1/90 = 4/90 =2/45.
This is and b together part of work now one day work = 45/2 = 22.5 days.
VICKMA said:
7 years ago
Here A is thrice EFFICIENT than B.
A=1 B= 3
A takes 60days less than B to finish a work, This shows that if B takes to complete a work by "X" days. Then A will take X - 60 days to complete a piece of work.
We know that A=1.
B=3
A= X - 60
B= X (No.of day to complete a work).
Cross multiply: 3(X-60)=X => 3X-180=X,
-180=-2X => X= 90.
WORKING TOGETHER: A+B = 1/X-60 + 1/X.
We know that X = 90,
A+B = 1/90-60 + 1/90,
=1/30+1/90,
=(3+1)/90 => 4/90 => 2/ 45.
Therefore, A+B takes 45/2 days to complete a piece of work.
A+B = 22 1/2.
A=1 B= 3
A takes 60days less than B to finish a work, This shows that if B takes to complete a work by "X" days. Then A will take X - 60 days to complete a piece of work.
We know that A=1.
B=3
A= X - 60
B= X (No.of day to complete a work).
Cross multiply: 3(X-60)=X => 3X-180=X,
-180=-2X => X= 90.
WORKING TOGETHER: A+B = 1/X-60 + 1/X.
We know that X = 90,
A+B = 1/90-60 + 1/90,
=1/30+1/90,
=(3+1)/90 => 4/90 => 2/ 45.
Therefore, A+B takes 45/2 days to complete a piece of work.
A+B = 22 1/2.
Akshay Salekar said:
5 years ago
Hi, friends.
We know that A capability to do work is 3 times of B,ok
Then the the ratio of Efficiency is A:B=3:1
And the ratio of time (days) is A:B=1:3 ...(The ratio get reverse because Efficiency and time are inversely proportional)
Now,
Time taken by A to complete work = (X) day &
Time taken by B to complete work = (X+60) day.
*We compare the ratio of time
(X/X+60)=(1/3) get X = 30 ----> (1).
From (1) we get A need 30 Days and B need 90 days
Now take lcm of (A day and B-day).
That is LCM of (30 & 90).
A & B need to complete 90 work.
So, the efficiency of A is (3 w/d) & B's efficiency (1w/d).
When they together (A+B) = work done is (4w/d).
So (90w/(4w/d)) = 22 1/2.
We know that A capability to do work is 3 times of B,ok
Then the the ratio of Efficiency is A:B=3:1
And the ratio of time (days) is A:B=1:3 ...(The ratio get reverse because Efficiency and time are inversely proportional)
Now,
Time taken by A to complete work = (X) day &
Time taken by B to complete work = (X+60) day.
*We compare the ratio of time
(X/X+60)=(1/3) get X = 30 ----> (1).
From (1) we get A need 30 Days and B need 90 days
Now take lcm of (A day and B-day).
That is LCM of (30 & 90).
A & B need to complete 90 work.
So, the efficiency of A is (3 w/d) & B's efficiency (1w/d).
When they together (A+B) = work done is (4w/d).
So (90w/(4w/d)) = 22 1/2.
Sureshkumar said:
1 decade ago
Another easy way 2 find out:
1st put the ratio i.e.1:3(A:B)
2nd the condition given here is A can work less than 60 days
So, find out the probability that matches with the ratio condition(A&B must be difference 60 here) for eg:let we take as A as 20 therefore B must be 60(here we get the difference as 40 only)according to 1:3 which cant satisfy
The given condition(A less than B by 60 days) suppose you take A as 30 means you get B as 90 which is greater than 60 days
of A....A=30 B=90 A's 1 day work=1/30
B's 1 day work=1/90 A+B's 1 day work =1/30+1/90=4/90 here they are not given to find out as 1day work...so take as 90/4=22.5 <==> 22(1/2).
1st put the ratio i.e.1:3(A:B)
2nd the condition given here is A can work less than 60 days
So, find out the probability that matches with the ratio condition(A&B must be difference 60 here) for eg:let we take as A as 20 therefore B must be 60(here we get the difference as 40 only)according to 1:3 which cant satisfy
The given condition(A less than B by 60 days) suppose you take A as 30 means you get B as 90 which is greater than 60 days
of A....A=30 B=90 A's 1 day work=1/30
B's 1 day work=1/90 A+B's 1 day work =1/30+1/90=4/90 here they are not given to find out as 1day work...so take as 90/4=22.5 <==> 22(1/2).
Salman said:
10 years ago
So much confusing answer given. This is basically ratio problem.
60 days less means you have to take ratio of time and solve the problem. A is thrice as better as B means. B takes thrice time compared to A.
i.e Ratio of time taken by A/B = 1/3.
If B takes x days then A takes x-60 days time to complete the work.
i.e Ratio of time taken by A/B = x-60/x.
Therefore 1/3 = x-60/x.
Solve to get x = 90 therefore B takes 90 days and A takes 30 days.
Daily Work of A = 1/30.
Daily Work of B = 1/90.
Adding work of A and B.
Daily work of A and B is 4/90.
So time taken for both A and B to complete the work is 90/4 = 221/2 days!
Simple as that!
60 days less means you have to take ratio of time and solve the problem. A is thrice as better as B means. B takes thrice time compared to A.
i.e Ratio of time taken by A/B = 1/3.
If B takes x days then A takes x-60 days time to complete the work.
i.e Ratio of time taken by A/B = x-60/x.
Therefore 1/3 = x-60/x.
Solve to get x = 90 therefore B takes 90 days and A takes 30 days.
Daily Work of A = 1/30.
Daily Work of B = 1/90.
Adding work of A and B.
Daily work of A and B is 4/90.
So time taken for both A and B to complete the work is 90/4 = 221/2 days!
Simple as that!
Piyasa Dey said:
1 decade ago
If A does a work in 1 day.
therefor B does the same work in 3 days since A is thrice as good as workman as B.
Let A completes the work in x days, B will take (x + 60) days more than A takes.
Therefore 1:3 :: x :(x + 60).
Now according to the formula if a:b :: c:d.
Then it is considered as (a * d) = (b*c).
Applying this formula we get 1*(x + 60) = 3*x.
By solving we get x= 30 i.e A takes 30 days to complete the work.
Therefore B will take (30+60)=90 days.
A's one day work = 1/30 days.
B's one day work = 1/90 days.
A+B one day work = (1/30)+(1/90) = 4/90 days.
Therefore A and B can finish the work in = 90/4.
therefor B does the same work in 3 days since A is thrice as good as workman as B.
Let A completes the work in x days, B will take (x + 60) days more than A takes.
Therefore 1:3 :: x :(x + 60).
Now according to the formula if a:b :: c:d.
Then it is considered as (a * d) = (b*c).
Applying this formula we get 1*(x + 60) = 3*x.
By solving we get x= 30 i.e A takes 30 days to complete the work.
Therefore B will take (30+60)=90 days.
A's one day work = 1/30 days.
B's one day work = 1/90 days.
A+B one day work = (1/30)+(1/90) = 4/90 days.
Therefore A and B can finish the work in = 90/4.
Post your comments here: