Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
281 comments Page 1 of 29.

Dhananjay said:   3 years ago
3x-x = 60,
x = 30.

A=90 B=30.

LCM(90,30) == 90unit.

for A -------> 1unit/day.
for B ------->3unit/day.

Total unit of work = 90/4 = 22.5.
(146)

SIBAJI MALLIK said:   2 years ago
A : B
1 : 3.

Difference = 2.
i.e 2 part = 60 (given),
1 part= 60/2 = 30.
A can do it in 30 days.
B can do it in 90 days.

A's 1 day's work= 1/30 and,
B's 1 day's work= 1/90,
A+B 1 day's work = 1/30 + 1/90 = 2/45.
They can do it in 45/2 days.
(108)

Vpk said:   2 years ago
A B
(x-60) x
B=3A;

x = 3(x-60);
x = 3x - 180;
2x = 180;
x = 90;
B = 90 days
A = 30 days.

Work done in 1 day A and B together => 1/30 + 1/90=2/45;
Whole work is will be done 45/2=>22 1/2;
(103)

Taukir said:   9 months ago
A takes time = x days.
So, B takes time = 3x days
Now, 3x - x = 60 days
X = 30
3x = 90
1/30 + 1/90 = 1/20 (working together in 1 day).
So, They can do the whole work in 20 days.
(84)

Furquan Shiekh said:   10 months ago
Suppose A takes x days to complete the work.
Therefore, B will take 3x days.
Now, x = 3x- 60.
x= 30 days.

Thus A takes 30 days and B takes 90 days.
Therefore work done by both in 1 day will be (1/30 + 1/90) = 4/90.

Therefore they take (90/4) = 22.5 days to complete the work.
(73)

Suhas Wankhede said:   2 years ago
Given Equation
A = 3B ---> (i)
Let B=x days --> (ii)
Given:
A = x - 60 days ---> (iii)

Compare i and iii;
x-60 = 3B (i.e B=x).
x-60 = 3x,
x = 30.
A = 3 * 30 = 90 days.
B = 30 days.
LCM 90.
A's Efficiency 1.
b's Efficiency 3.
90/3+1 = 22 1/2 days.
(64)

Aya adel said:   2 years ago
a : b
1 : 3.

And x-60:x

Then 3(x - 60) = x.
3x-180 = x,
2x = 180,
x = 90.

a = 90 - 60 = 30
b = 90
1\a + 1\b = 1\30 + 1\90 = 2\45.
a + b = 45\2.
So, the answer is 22 1\2.
(57)

Harsha said:   2 years ago
A takes x-60 days.
B takes x days.
If A does work in 1 day then B takes 3 days.
So,
1/(x-60) = 1/x
Solving this we get x = 90
Now, A+B can do work in 1/90 + 3/90.
We get 45/2.
(49)

Man said:   3 years ago
Given A:B = 1:3 => B = 3A.'

Let assume A can complete work in x days which implies B = 3x
and also given B-A = 60 => 3x-x = 60 => 2x = 60 => x = (60/2) => 30

therefore A can complete the work in 30 days. and B can complete the work in 3*30 = 90 days
1 day work of A & B together = 1/30 + 1/90 = 4/90.

If they both do 4/90 work in one day so to complete the whole 1 work they will take;
(4/90) * x = 1.
x = 90/4 = 45/2 = 22 1/2.
(47)

Nikita raisadhar said:   5 months ago
3x - x=60
2x = 60
x = 30
B = 3x = 3 x 30 = 90.
A+B = 1/30 + 1/90,
= 3 + 1/90,
= 4/90,
= 2/42,
= 45/2,
= 22 1/2.
(46)


Post your comments here:

Your comments will be displayed after verification.