Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
| If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
| 2 |
So, A takes 30 days to do the work.
| A's 1 day's work = | 1 |
| 30 |
| B's 1 day's work = | 1 |
| 90 |
| (A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
| 30 | 90 | 90 | 45 |
A and B together can do the work in |
45 | = 22 | 1 | days. |
| 2 | 2 |
Discussion:
284 comments Page 2 of 29.
Kamal Thakur said:
3 years ago
Let A complete work in = x days.
B will complete work in = 3x days.
(As a is 3x sufficient so b will take 3x much time)
Also, A take 60 days less,
So days were taken by B - 60 = days taken by A
So equation will be;
3x - 60 = x,
2x = 60,
x = 30.
So A completes work in 30 days and B in 30 X x = 90
A 1-day work = 1/30,
B 1 day work = 1/90,
1 day work of A & B together = 1/30 + 1/90 = 4/90.
If they both do 4/90 work in one day so to complete the whole 1 work they will take
4/90 X x = 1.
x = 90/4 = 45/2 = 22 1/2.
B will complete work in = 3x days.
(As a is 3x sufficient so b will take 3x much time)
Also, A take 60 days less,
So days were taken by B - 60 = days taken by A
So equation will be;
3x - 60 = x,
2x = 60,
x = 30.
So A completes work in 30 days and B in 30 X x = 90
A 1-day work = 1/30,
B 1 day work = 1/90,
1 day work of A & B together = 1/30 + 1/90 = 4/90.
If they both do 4/90 work in one day so to complete the whole 1 work they will take
4/90 X x = 1.
x = 90/4 = 45/2 = 22 1/2.
(42)
Farheen Pathan said:
3 years ago
As A is thrice good than B then the Ratio of work done together is:
A : B
3 : 1
As A do work 60 days less than B , Suppose;
A : B
30 : 90---->LCM = 90,
(30×3)----->3u of A+1u of B =4u,
I.e 90/4 = 45/2 = 22(1/2).
A : B
3 : 1
As A do work 60 days less than B , Suppose;
A : B
30 : 90---->LCM = 90,
(30×3)----->3u of A+1u of B =4u,
I.e 90/4 = 45/2 = 22(1/2).
(35)
Ajishwarya said:
4 months ago
A is thrice as good a workman as B:
So, A = 3 B.
Substitute A as 1/60.
1/60*3 = B.
1/180 = B
Working together :
A + B = 1/60 + 1/180.
= 4/180,
= 1/45 = 45 Days.
So, A = 3 B.
Substitute A as 1/60.
1/60*3 = B.
1/180 = B
Working together :
A + B = 1/60 + 1/180.
= 4/180,
= 1/45 = 45 Days.
(29)
Abhirup Paul said:
2 years ago
A is thrice as good as workman as B and therefore can finish a job in 60 days less than B. Working together, they can do it in:
A = 3x, B= 1x ----> {1}
Here A's efficiency = 3.
B's efficiency = 1.
The Sum of their efficiency is 4 (we will need this later on).
According to the question:
A = 3x - 60.
Therefore 1 day's work of A and B is:
1/(3x-60) = 1/(x).
By solving we get x = 30
By putting the value of x in eqn {1}
We get A= 3 X 30 = 90 days.
B = 30 days.
By working together, they can do it in:
90/4 days.
By further solving, we get 22 1/2 days.
A = 3x, B= 1x ----> {1}
Here A's efficiency = 3.
B's efficiency = 1.
The Sum of their efficiency is 4 (we will need this later on).
According to the question:
A = 3x - 60.
Therefore 1 day's work of A and B is:
1/(3x-60) = 1/(x).
By solving we get x = 30
By putting the value of x in eqn {1}
We get A= 3 X 30 = 90 days.
B = 30 days.
By working together, they can do it in:
90/4 days.
By further solving, we get 22 1/2 days.
(27)
Subhranil Mondal said:
11 months ago
Assume B can do it in x days.
So A can in x/3 days.
x - x/3 = 60.
then x = 90.
So B can do the work in 90 days.
A can do it in 90/3 = 30 days.
A and B together can do it in 90 * 30/90 + 30 = 22.5 (Ans).
So A can in x/3 days.
x - x/3 = 60.
then x = 90.
So B can do the work in 90 days.
A can do it in 90/3 = 30 days.
A and B together can do it in 90 * 30/90 + 30 = 22.5 (Ans).
(25)
HARINI said:
4 years ago
Given;
A = 3B;
A = B - 60.
Substitute A = 3B in 2nd equation(a=b-60).
3B = B-60
B = 30.
Therefore; A = 3B = 90.
A+B = (1/30 + 1/90) = 2/45.
So, the answer is 22(1/2).
A = 3B;
A = B - 60.
Substitute A = 3B in 2nd equation(a=b-60).
3B = B-60
B = 30.
Therefore; A = 3B = 90.
A+B = (1/30 + 1/90) = 2/45.
So, the answer is 22(1/2).
(24)
D venkat raman said:
2 years ago
A is thrice as good as workman as B and therefore can finish a job in 60 days - question
Just think A thrice is 90;
How means;
A is thrice as b;
For A assume as x;
then B assume as 2x;
then C assume as 3x;
in question they thrice -- so we can assume thrice as 3x;
if one is 30 means.
then twice as 60.
then thrice as 90.
So , one day of the work is 1/30, then thrice day of the work is 1/90.
Working together A+B;
1/30+1/90;then.
Then take lcm it will give 90.
Then check whether the 90 is in a and b
3+1/90;
4/90;
2/45;
Then reciprocal it or div it will give 22 1/2.
Just think A thrice is 90;
How means;
A is thrice as b;
For A assume as x;
then B assume as 2x;
then C assume as 3x;
in question they thrice -- so we can assume thrice as 3x;
if one is 30 means.
then twice as 60.
then thrice as 90.
So , one day of the work is 1/30, then thrice day of the work is 1/90.
Working together A+B;
1/30+1/90;then.
Then take lcm it will give 90.
Then check whether the 90 is in a and b
3+1/90;
4/90;
2/45;
Then reciprocal it or div it will give 22 1/2.
(20)
Raseswari said:
9 months ago
I am not understanding this question.
Anyone help me to get it be explaining it along with the formulas?
Anyone help me to get it be explaining it along with the formulas?
(20)
Jagadish Behera said:
3 years ago
"A" is 3 times more than" B" (efficiency)
Difference = 60 days
3x-x = 60
X = 30days This is" B"
A=3 * 30 = 90 days.
So Total work =180
A=2 WORK
B=6 WORK
A+B TOGETHER CAN DO IN 180/8 = 22.5 DAYS.
Difference = 60 days
3x-x = 60
X = 30days This is" B"
A=3 * 30 = 90 days.
So Total work =180
A=2 WORK
B=6 WORK
A+B TOGETHER CAN DO IN 180/8 = 22.5 DAYS.
(14)
Lalith kumar said:
5 months ago
First, A is thrice as good as B means.
If a takes a day to complete work, then b takes 3 days to complete the same work.
Here, time is inversely proportional to work.
So if b takes time T to complete, then a takes T/3 to complete.
In question, they mentioned that the time diff is 60 days.
So, T - T/3 = 60.
2T/3 = 60.
T = 90.
Now, calculate the combined work and how many days it will take.
1/30 + 1/90 = 2/45 = 22.5.
If a takes a day to complete work, then b takes 3 days to complete the same work.
Here, time is inversely proportional to work.
So if b takes time T to complete, then a takes T/3 to complete.
In question, they mentioned that the time diff is 60 days.
So, T - T/3 = 60.
2T/3 = 60.
T = 90.
Now, calculate the combined work and how many days it will take.
1/30 + 1/90 = 2/45 = 22.5.
(14)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers


A and B together can do the work in