Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
284 comments Page 2 of 29.

Kamal Thakur said:   3 years ago
Let A complete work in = x days.
B will complete work in = 3x days.

(As a is 3x sufficient so b will take 3x much time)
Also, A take 60 days less,
So days were taken by B - 60 = days taken by A
So equation will be;
3x - 60 = x,
2x = 60,
x = 30.

So A completes work in 30 days and B in 30 X x = 90
A 1-day work = 1/30,
B 1 day work = 1/90,

1 day work of A & B together = 1/30 + 1/90 = 4/90.

If they both do 4/90 work in one day so to complete the whole 1 work they will take
4/90 X x = 1.
x = 90/4 = 45/2 = 22 1/2.
(42)

Farheen Pathan said:   3 years ago
As A is thrice good than B then the Ratio of work done together is:

A : B
3 : 1

As A do work 60 days less than B , Suppose;
A : B
30 : 90---->LCM = 90,
(30×3)----->3u of A+1u of B =4u,
I.e 90/4 = 45/2 = 22(1/2).
(35)

Ajishwarya said:   4 months ago
A is thrice as good a workman as B:
So, A = 3 B.
Substitute A as 1/60.
1/60*3 = B.
1/180 = B
Working together :
A + B = 1/60 + 1/180.
= 4/180,
= 1/45 = 45 Days.
(29)

Abhirup Paul said:   2 years ago
A is thrice as good as workman as B and therefore can finish a job in 60 days less than B. Working together, they can do it in:

A = 3x, B= 1x ----> {1}
Here A's efficiency = 3.
B's efficiency = 1.

The Sum of their efficiency is 4 (we will need this later on).

According to the question:
A = 3x - 60.

Therefore 1 day's work of A and B is:
1/(3x-60) = 1/(x).
By solving we get x = 30
By putting the value of x in eqn {1}
We get A= 3 X 30 = 90 days.
B = 30 days.

By working together, they can do it in:
90/4 days.
By further solving, we get 22 1/2 days.
(27)

Subhranil Mondal said:   11 months ago
Assume B can do it in x days.
So A can in x/3 days.
x - x/3 = 60.
then x = 90.
So B can do the work in 90 days.
A can do it in 90/3 = 30 days.
A and B together can do it in 90 * 30/90 + 30 = 22.5 (Ans).
(25)

HARINI said:   4 years ago
Given;

A = 3B;
A = B - 60.

Substitute A = 3B in 2nd equation(a=b-60).
3B = B-60
B = 30.

Therefore; A = 3B = 90.

A+B = (1/30 + 1/90) = 2/45.
So, the answer is 22(1/2).
(24)

D venkat raman said:   2 years ago
A is thrice as good as workman as B and therefore can finish a job in 60 days - question
Just think A thrice is 90;
How means;

A is thrice as b;
For A assume as x;
then B assume as 2x;
then C assume as 3x;

in question they thrice -- so we can assume thrice as 3x;
if one is 30 means.
then twice as 60.
then thrice as 90.
So , one day of the work is 1/30, then thrice day of the work is 1/90.

Working together A+B;
1/30+1/90;then.
Then take lcm it will give 90.
Then check whether the 90 is in a and b
3+1/90;
4/90;
2/45;
Then reciprocal it or div it will give 22 1/2.
(20)

Raseswari said:   9 months ago
I am not understanding this question.

Anyone help me to get it be explaining it along with the formulas?
(20)

Jagadish Behera said:   3 years ago
"A" is 3 times more than" B" (efficiency)

Difference = 60 days

3x-x = 60

X = 30days This is" B"

A=3 * 30 = 90 days.

So Total work =180

A=2 WORK
B=6 WORK

A+B TOGETHER CAN DO IN 180/8 = 22.5 DAYS.
(14)

Lalith kumar said:   5 months ago
First, A is thrice as good as B means.

If a takes a day to complete work, then b takes 3 days to complete the same work.

Here, time is inversely proportional to work.

So if b takes time T to complete, then a takes T/3 to complete.
In question, they mentioned that the time diff is 60 days.
So, T - T/3 = 60.
2T/3 = 60.
T = 90.
Now, calculate the combined work and how many days it will take.
1/30 + 1/90 = 2/45 = 22.5.
(14)


Post your comments here:

Your comments will be displayed after verification.