1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Answer: Option
Explanation:
| A's 1 day's work = | 1 | ; |
| 15 |
| B's 1 day's work = | 1 | ; |
| 20 |
| (A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 7 | . |
| 15 | 20 | 60 |
| (A + B)'s 4 day's work = | ![]() |
7 | x 4 | ![]() |
= | 7 | . |
| 60 | 15 |
| Therefore, Remaining work = | ![]() |
1 - | 7 | ![]() |
= | 8 | . |
| 15 | 15 |
2.
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Answer: Option
Explanation:
| (A + B + C)'s 1 day's work = | 1 | , |
| 4 |
| A's 1 day's work = | 1 | , |
| 16 |
| B's 1 day's work = | 1 | . |
| 12 |
C's 1 day's work = |
1 | - | ![]() |
1 | + | 1 | ![]() |
= | ![]() |
1 | - | 7 | ![]() |
= | 5 | . |
| 4 | 16 | 12 | 4 | 48 | 48 |
| So, C alone can do the work in | 48 | = 9 | 3 | days. |
| 5 | 5 |
3.
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Answer: Option
Explanation:
| A's 2 day's work = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
| 20 | 10 |
| (A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 6 | = | 1 | . |
| 20 | 30 | 60 | 60 | 10 |
| Work done in 3 days = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
| 10 | 10 | 5 |
| Now, | 1 | work is done in 3 days. |
| 5 |
Whole work will be done in (3 x 5) = 15 days.
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
| If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
| 2 |
So, A takes 30 days to do the work.
| A's 1 day's work = | 1 |
| 30 |
| B's 1 day's work = | 1 |
| 90 |
| (A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
| 30 | 90 | 90 | 45 |
A and B together can do the work in |
45 | = 22 | 1 | days. |
| 2 | 2 |
5.
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Answer: Option
Explanation:
| C's 1 day's work = | 1 | - | ![]() |
1 | + | 1 | ![]() |
= | 1 | - | 7 | = | 1 | . |
| 3 | 6 | 8 | 3 | 24 | 24 |
| A's wages : B's wages : C's wages = | 1 | : | 1 | : | 1 | = 4 : 3 : 1. |
| 6 | 8 | 24 |
C's share (for 3 days) = Rs. |
![]() |
3 x | 1 | x 3200 | ![]() |
= Rs. 400. |
| 24 |