Aptitude - Time and Work
Exercise : Time and Work - General Questions
- Time and Work - Formulas
- Time and Work - General Questions
- Time and Work - Data Sufficiency 1
- Time and Work - Data Sufficiency 2
- Time and Work - Data Sufficiency 3
26.
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
Answer: Option
Explanation:
(A + B + C)'s 1 day's work = | 1 | ; |
6 |
(A + B)'s 1 day's work = | 1 | ; |
8 |
(B + C)'s 1 day's work = | 1 | . |
12 |
(A + C)'s 1 day's work |
|
||||||||||||||
|
|||||||||||||||
|
|||||||||||||||
|
So, A and C together will do the work in 8 days.
27.
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
Answer: Option
Explanation:
(B + C)'s 1 day's work = | 1 | + | 1 | = | 7 | . | ||
9 | 12 | 36 |
Work done by B and C in 3 days = | 7 | x 3 | = | 7 | . | ||
36 | 12 |
Remaining work = | 1 - | 7 | = | 5 | . | ||
12 | 12 |
Now, | 1 | work is done by A in 1 day. |
24 |
So, | 5 | work is done by A in | 24 x | 5 | = 10 days. | ||
12 | 12 |
28.
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Answer: Option
Explanation:
Work done by X in 8 days = | 1 | x 8 | = | 1 | . | ||
40 | 5 |
Remaining work = | 1 - | 1 | = | 4 | . | ||
5 | 5 |
Now, | 4 | work is done by Y in 16 days. |
5 |
Whole work will be done by Y in | 16 x | 5 | = 20 days. | ||
4 |
X's 1 day's work = | 1 | , Y's 1 day's work = | 1 | . |
40 | 20 |
(X + Y)'s 1 day's work = | 1 | + | 1 | = | 3 | . | ||
40 | 20 | 40 |
Hence, X and Y will together complete the work in | 40 | = 13 | 1 | days. | ||
3 | 3 |
29.
A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be done by A alone in :
Answer: Option
Explanation:
(A's 1 day's work) : (B's 1 day's work) = | 7 | : 1 = 7 : 4. |
4 |
Let A's and B's 1 day's work be 7x and 4x respectively.
Then, 7x + 4x = | 1 | 11x = | 1 | x = | 1 | . |
7 | 7 | 77 |
A's 1 day's work = | 1 | x 7 | = | 1 | . | ||
77 | 11 |
30.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
Answer: Option
Explanation:
Let A's 1 day's work = x and B's 1 day's work = y.
Then, x + y = | 1 | and 16x + 44y = 1. |
30 |
Solving these two equations, we get: x = | 1 | and y = | 1 |
60 | 60 |
B's 1 day's work = | 1 | . |
60 |
Hence, B alone shall finish the whole work in 60 days.
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers