Aptitude - Time and Work
Exercise : Time and Work - General Questions
- Time and Work - Formulas
- Time and Work - General Questions
- Time and Work - Data Sufficiency 1
- Time and Work - Data Sufficiency 2
- Time and Work - Data Sufficiency 3
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
Answer: Option
Explanation:
Suppose A, B and C take x, | x | and | x | days respectively to finish the work. |
2 | 3 |
Then, | ![]() |
1 | + | 2 | + | 3 | ![]() |
= | 1 |
x | x | x | 2 |
![]() |
6 | = | 1 |
x | 2 |
x = 12.
So, B takes (12/2) = 6 days to finish the work.
22.
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
Answer: Option
Explanation:
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 1 | . |
15 | 10 | 6 |
Work done by A and B in 2 days = | ![]() |
1 | x 2 | ![]() |
= | 1 | . |
6 | 3 |
Remaining work = | ![]() |
1 - | 1 | ![]() |
= | 2 | . |
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
15 |
![]() |
2 | work will be done by a in | ![]() |
15 x | 2 | ![]() |
= 10 days. |
3 | 3 |
Hence, the total time taken = (10 + 2) = 12 days.
23.
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
Answer: Option
Explanation:
2(A + B + C)'s 1 day's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 15 | = | 1 | . |
30 | 24 | 20 | 120 | 8 |
Therefore, (A + B + C)'s 1 day's work = | 1 | = | 1 | . |
2 x 8 | 16 |
Work done by A, B, C in 10 days = | 10 | = | 5 | . |
16 | 8 |
Remaining work = | ![]() |
1 - | 5 | ![]() |
= | 3 | . |
8 | 8 |
A's 1 day's work = | ![]() |
1 | - | 1 | ![]() |
= | 1 | . |
16 | 24 | 48 |
Now, | 1 | work is done by A in 1 day. |
48 |
So, | 3 | work will be done by A in | ![]() |
48 x | 3 | ![]() |
= 18 days. |
8 | 8 |
24.
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
Answer: Option
Explanation:
Ratio of rates of working of A and B = 2 : 1.
So, ratio of times taken = 1 : 2.
B's 1 day's work = | 1 | . |
12 |
![]() |
1 | ; (2 times of B's work) |
6 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 3 | = | 1 | . |
6 | 12 | 12 | 4 |
So, A and B together can finish the work in 4 days.
25.
Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?
Answer: Option
Explanation:
(20 x 16) women can complete the work in 1 day.
![]() |
1 | . |
320 |
(16 x 15) men can complete the work in 1 day.
![]() |
1 |
240 |
So, required ratio |
|
||||||
|
|||||||
= 4 : 3 (cross multiplied) |
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers