Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 21)
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
Answer: Option
Explanation:
Suppose A, B and C take x, | x | and | x | days respectively to finish the work. |
2 | 3 |
Then, | ![]() |
1 | + | 2 | + | 3 | ![]() |
= | 1 |
x | x | x | 2 |
![]() |
6 | = | 1 |
x | 2 |
x = 12.
So, B takes (12/2) = 6 days to finish the work.
Discussion:
67 comments Page 1 of 7.
Tanuja Sinha said:
6 months ago
A = 2B, A = 3C.
So A = 2B = 3C.
A : B : C = (1/1) × 6 : (1/2) × 6 : (1/3)×6.
= 6 : 3 : 2.
A and B together do work in 2 days (Nowhere mention that A, B and C are doing simultaneously, so taking A and B as contains B and we have to find B alone).
So, Total work = (6 + 3) × 2 = 18
B can do alone = 18/3 = 6 days.
So A = 2B = 3C.
A : B : C = (1/1) × 6 : (1/2) × 6 : (1/3)×6.
= 6 : 3 : 2.
A and B together do work in 2 days (Nowhere mention that A, B and C are doing simultaneously, so taking A and B as contains B and we have to find B alone).
So, Total work = (6 + 3) × 2 = 18
B can do alone = 18/3 = 6 days.
(2)
Karthick M said:
2 years ago
To simple method is:
A = 2B or A=3B
(A+B)'s 1day work = 1/2=(2B+B)'s 1day work
1/2 = 3B's 1-day work
ie, B's 1 day work = 1/6
So, B's whole work done is in 6 days.
A = 2B or A=3B
(A+B)'s 1day work = 1/2=(2B+B)'s 1day work
1/2 = 3B's 1-day work
ie, B's 1 day work = 1/6
So, B's whole work done is in 6 days.
(7)
Mahendra said:
3 years ago
Assume total work iso no of chairs from the give no of chair made per one day as per efficiency
A : B : C = 1 : 2 : 3.
So total chairs is 6 in one day.
Total days they together : 2 days.
So, total works = 6 * 2 = 12.
B alone can take = 12/2 = 6 days.
A : B : C = 1 : 2 : 3.
So total chairs is 6 in one day.
Total days they together : 2 days.
So, total works = 6 * 2 = 12.
B alone can take = 12/2 = 6 days.
(30)
Banjeet said:
4 years ago
A : B : C = 6 : 3 : 2,
11*2= 22 work,
So, B doing = (3/11) * 22 = 6 days.
11*2= 22 work,
So, B doing = (3/11) * 22 = 6 days.
(20)
Tyson said:
4 years ago
As the question says,
The time taken by A is twice that of B and thrice that of C, so
This means that;
Efficiency,
A=2*B=3*C
Efficiency is inversely proportional to the time taken to complete a task.
Time ratio
A/B=2/1,
A/C=3/1
So, the Efficiency ratio
A/B=1/2,
A/C=1/3
=>A/B/C=1/2/3.
A:B:C=1:2:3.
So in terms of RATIO,
Let 1-day work of A,B, C be 1unit, 2unit, 3unit.
i.e. work for A: 1 Day= 1 U---->eqn 1
work for B: 1 Day= 2 U----> eqn 2
Work for C: 1 Day= 3 U----eqn 3
Work for A+B+C: 1 Day= 6 U.
2 Day=12U----eqn iv
[Total work(12U) completes in Time =2days(given)
i.e.Total Works time taken by A+B+C, Time =2days]
Comparing (eqn ii & iv) find B can do the work alone
Work for B: 1 Day = 2 U ----> eqn 2
work for B: 3x2 Day = 6x2 U.
6 DAYS = 12 U.
B alone do the work in time = 6 days.
The time taken by A is twice that of B and thrice that of C, so
This means that;
Efficiency,
A=2*B=3*C
Efficiency is inversely proportional to the time taken to complete a task.
Time ratio
A/B=2/1,
A/C=3/1
So, the Efficiency ratio
A/B=1/2,
A/C=1/3
=>A/B/C=1/2/3.
A:B:C=1:2:3.
So in terms of RATIO,
Let 1-day work of A,B, C be 1unit, 2unit, 3unit.
i.e. work for A: 1 Day= 1 U---->eqn 1
work for B: 1 Day= 2 U----> eqn 2
Work for C: 1 Day= 3 U----eqn 3
Work for A+B+C: 1 Day= 6 U.
2 Day=12U----eqn iv
[Total work(12U) completes in Time =2days(given)
i.e.Total Works time taken by A+B+C, Time =2days]
Comparing (eqn ii & iv) find B can do the work alone
Work for B: 1 Day = 2 U ----> eqn 2
work for B: 3x2 Day = 6x2 U.
6 DAYS = 12 U.
B alone do the work in time = 6 days.
(2)
Abhishek said:
4 years ago
Let's assume.
C takes 4 days to do X work.
B takes 6 days for the same X work.
A takes 12 days for the same X work.
so, efficiency
A = 1/12.
B = 1/6.
c = 1/4.
So, as they all together takes 2 days to work,
x/(1/12)+(1/6)+(1/4) = 2
From that, we got X ( total work ) = 1
So time taken alone by;
B = 1/(1/) = 6 days.
C takes 4 days to do X work.
B takes 6 days for the same X work.
A takes 12 days for the same X work.
so, efficiency
A = 1/12.
B = 1/6.
c = 1/4.
So, as they all together takes 2 days to work,
x/(1/12)+(1/6)+(1/4) = 2
From that, we got X ( total work ) = 1
So time taken alone by;
B = 1/(1/) = 6 days.
(1)
Subhasish baul said:
5 years ago
A - 12.
B - 6.
C - 4.
Work as satisfied to take together 2day finished.
Efficiency A 1 B 2 C 3.
Total work 12.
Total efficiency 6.
Finished together 12 ÷ 6 = 2day satisfied
**B alone do in 12 ÷ 2 = 6 days.
B - 6.
C - 4.
Work as satisfied to take together 2day finished.
Efficiency A 1 B 2 C 3.
Total work 12.
Total efficiency 6.
Finished together 12 ÷ 6 = 2day satisfied
**B alone do in 12 ÷ 2 = 6 days.
Manohar said:
6 years ago
Simply:
6:3:1 = 9
9*2 = 18.
18/3 = 6.
6:3:1 = 9
9*2 = 18.
18/3 = 6.
(2)
Rajshekar said:
6 years ago
A x.
B 2x.
C 3x.
A+B+B = 1/2,
X+2x+3x = 1/2.
6x=1/2.
X=1/12.
So, be alone =2x = 2 * 1/12 = 1/6 = 6days.
B 2x.
C 3x.
A+B+B = 1/2,
X+2x+3x = 1/2.
6x=1/2.
X=1/12.
So, be alone =2x = 2 * 1/12 = 1/6 = 6days.
(9)
Rexi said:
6 years ago
Simply, it is solved by;
A=2B ; A=3C.
A/2=B ; A/3=C ---> time,
2/A=B; 3/A=C ---> efficiency,
1/A+2/A+3/A = 1/2 ---> A+B+C=1/2.
A = 12,
B = 6,
C = 4.
A=2B ; A=3C.
A/2=B ; A/3=C ---> time,
2/A=B; 3/A=C ---> efficiency,
1/A+2/A+3/A = 1/2 ---> A+B+C=1/2.
A = 12,
B = 6,
C = 4.
(4)
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers