21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
4 days
6 days
8 days
12 days
Answer: Option
Explanation:

Suppose A, B and C take x, x and x days respectively to finish the work.
2 3

Then, 1 + 2 + 3 = 1
x x x 2

6 = 1
x 2

x = 12.

So, B takes (12/2) = 6 days to finish the work.

Discussion:
67 comments Page 7 of 7.

Keyan said:   1 decade ago
How to solve it in 1:2:3 basis?

Kumar said:   1 decade ago
How the work equation became as (1/x)+(2/x)+(3/x)=1/2

Ananth said:   1 decade ago
How the total work equation became as (1/x)+(2/x)+(3/x)=1/2

Please explain.

Srihari said:   1 decade ago
Hi Meera,

It is not right method because A+B+C's 1 day work is only 1/2 not 1/6.

Meera said:   1 decade ago
A+B+C's 1 days work is = 1/6.

Therefore 2'days work (A+B+C) is=1/6*2=3.

B can do the work alone (2*3) =6.

So B takes 6 days to finish the work.

Is it right method? please anyone tell me.

Ritanjali natua said:   1 decade ago
1/x+2/x+3/x=6/x

Afua said:   1 decade ago
Where's 6 coming from?