Discussion Forum : Time and Work - General Questions (Q.No. 21)
21.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
4 days
6 days
8 days
12 days
Answer: Option
Explanation:

Suppose A, B and C take x, x and x days respectively to finish the work.
2 3

Then, 1 + 2 + 3 = 1
x x x 2

6 = 1
x 2

x = 12.

So, B takes (12/2) = 6 days to finish the work.

Discussion:
68 comments Page 6 of 7.

Aashish said:   1 decade ago
Can anyone please explain me how 1/x comes? Because, I formed the equation as x+x/2+x/3=2 and got the wrong answer :-(

Kiran said:   1 decade ago
B=2A
C=3A
A+B+C=2days
A+2A+3A=2days
so,6A=2days
A only takes (6*2)=12 days
B=2A,so B only takes (12/2)=6days

Md Ali Umar said:   1 decade ago
Hi Mini you are making equ. 2A=B & 3A=C, but so many people a making equ. A=2B & A=3C .

Which one s correct, but both one is getting same answer. I'm confussing in this prob. Pls any one describe it ?

Divya said:   1 decade ago
A=2B=3C

A+B+C=2 ----(EQ.1)

WRITING a and c in terms of b,

A=2B, C=2B/3
IN EQ.1,

2B+B+2B/3=2

3B+2B/3=2


(9B+2B)/3=2

9B+2B=2*3

11B=6

B=6/11

that means, out of 11 days, b alone completes 6 days of work.

Mini said:   1 decade ago
A takes twice much time them B i.e. 2A=B...(i)
A takes thrice much time thn C i.e. 3A=C...(ii)

It is given dat workin together they can finish in 2 days
so A+B+C=1/2
Now put B=2A AND C=3A in this equ...
A+B+C=1/2
A+2A+3A=1/2
6A=1/2
A=1/2*6=1/12
Now put the value of A in equ.(i)
.i.e B=2A
=2*1/12
=1/6
Therefore B takes 6 days to complete the work.

Manasa said:   1 decade ago
@nayana
GIVEN:
A=2B,A=3C
solution:
consider A can do work in X days
X=2B...B=X/2;X=2C...C=X/3;
B can complete work in X/2days,B's 1 day work is 2/X
C can complete work in X/3days,C's 1 day work is 3/X
A's 1 day work is 1/X.
(A+B+C) 1 days work is[(1/X)+(2/X)+(3/X)]=1/2
6/X=1/2
X=12
therefore b can do work in ;B=X/2=12/2=6 days

Nayana said:   1 decade ago
Hi,
Can any one exaplain why they have taken x,x/2,x/3, because in the question they have given A takes twice as much as B that means two times more than B but they are dividing it.

Student said:   1 decade ago
Hi thameem, hw can we write a+b=1/2? since three members are working is it not a+b+c=1/2....

please explain

Thameem said:   1 decade ago
here is another way of solving

given
a=2b
a=3c
a+b=1/2 (work from days)

use a's value in the equation

2b+b=1/2

then 3b=1/2
b=1/6

then b can done work alone in 6 days(days from work)

Lordy said:   1 decade ago
once c the question pls it is mentioned a is twice of b OR thrice of c then how can we divide x,x/2,x/3. if it is mentioned as and then we can decide right?