Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
283 comments Page 29 of 29.

Kumar said:   2 decades ago
Hi Guys,

Let me do the same thing with different values.

Given statement : "A is thrice as good as workman as B"
Time difference : 60 days.


If B takes 12 days to complete a work, A will take only 4 days to complete the same work.

So, B takes 12 days whereas A takes 4 days only (because A is thrice as good as B).

Here time difference is 12 - 4 = 8 days.

If the time difference is 8 days, B takes 12 days.

Similarly if the time difference is 60 days, then B takes (12/8 * 60) = 90 days.

...Rest thing you can understand from the explanation part.

Sundar said:   2 decades ago
Hi Friends!

The statement "A is thrice as good as workman as B" states that, If A complete a work in 1 day, B will take 3 days to complete the same work.

Therefore, if A takes 1 day, B takes 3 days, the time difference is 2 days.

If the time difference is 2 days, B takes 3 days to complete the work.

Similarly if the time difference is 60 days, then B takes (3/2*60) = 90 days.

Then A takes 90 - 60 = 30 days to complete the work.

It is very simple man.
(1)

Rajender said:   2 decades ago
Please tell me how you have calculated differece of time 2 days.


Post your comments here:

Your comments will be displayed after verification.