                        Dhaval Chaudhary said: 
                         
                        7 years ago
                
                A is correct answer 1-2-3-4-8-9.
Ref: R S Kurmi.
                Ref: R S Kurmi.
                        Bhargav said: 
                         
                        6 years ago
                
                According to me, Option A is the correct answer.
                
                        Vetan said: 
                         
                        6 years ago
                
                The critical path has the longest path and consumes maximum time and maximum resource 
So option B is correct.
1-2-3-5-6-7-8-9 = 24.
                So option B is correct.
1-2-3-5-6-7-8-9 = 24.
                        Karthi said: 
                         
                        6 years ago
                
                The critical path consist of the longest path duration 1-2-3-5-6-7-8-9 is 24 units.
                
                        Sagar Chavan said: 
                         
                        5 years ago
                
                Option A is correct.
                
                     (1)
                
            
                        S V Manikandan. said: 
                         
                        5 years ago
                
                Critical path is one, which consumes more time to complete. By this way, I can choose option B. The dummy loop is unaccountable.
                
                        Zeeshan_Pak said: 
                         
                        5 years ago
                
                A dummy activity can only become critical when its EST is the same as its LFT.
That's why D2 is considered critical and D1 is not.
So, Option B is right.
                That's why D2 is considered critical and D1 is not.
So, Option B is right.
                        Vanraj Gajarotar said: 
                         
                        5 years ago
                
                Option B is the right answer.
                
                        Aniket said: 
                         
                        4 years ago
                
                A dummy activity can be either critical or non-critical. It becomes a critical activity when the earlier start time and the latest finish time are equal.
                
                        Sukarma said: 
                         
                        4 years ago
                
                How to find the dummy activity? Anyone explain it.