Mechanical Engineering - Industrial Engineering and Production Management - Discussion

Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 15)
15.
In a network shown in the below figure, the critical path is along
1-2-3-4-8-9
1-2-3-5-6-7-8-9
1-2-3-4-7-8-9
1-2-5-6-7-8-9
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 1 of 4.

AMAL said:   10 years ago
Option [B] is the correct answer. The dummy activities are provided to show precedence before any activity. Here it is showing that after 3 we can go to point 5.

And the critical path is the one taking the longest time in cycle. There is nothing like we cannot consider dummy in critical path. 1-2-3-5-6-7-8-9 is taking 24 units that's why it will be critical path.

Janardhan reddy.G said:   10 years ago
1-2-3-4-8-9 = 21.

1-2-3-5-6-7-8-9 = 24.

1-2-5-6-7-8-9 = 22.

By comparing the critical path from the above, it is concluded that option B is correct. That is critical path is given by 1-2-3-5-6-7-8-9.

Whenever if we want to know the critical path we need to consider dummy activities also for the completion of project.

ONOSETALE said:   8 years ago
@ALL.

As an Industrial engineer, one of the function in a project is to obtain an optimal solution. However, I would suggest those against option B to study the algorithm of network diagram as regarding selecting the critical path(s).

Anand said:   7 years ago
CRITICAL Path:

A critical path consumes maximum resources. It is the longest path and consumes maximum time.

So the order of the network is 1-2-3-5-6-7-8-9.
Option B is correct.

Anomy said:   9 years ago
Critical path.

The sequence of stages determining the minimum time needed for an operation, especially when analyzed on a computer for a large organization.

Kannan said:   8 years ago
Option D is the correct answer. The dummy activity doesn't consume any resource or time. So we don't consider dummy activity while choosing a critical path.

Zeeshan_Pak said:   5 years ago
A dummy activity can only become critical when its EST is the same as its LFT.
That's why D2 is considered critical and D1 is not.
So, Option B is right.

Aniket said:   4 years ago
A dummy activity can be either critical or non-critical. It becomes a critical activity when the earlier start time and the latest finish time are equal.

Kuldip said:   1 decade ago
Critical path is one which takes more time to complete. So 1-2-5-6-7-8-9 is taking 22 days and other path 21 day so 1256789 should be the critical path.

Samuel said:   7 years ago
Exactly @Neeraj. But according to the definition, critical path is the longest path and consumes maximum time. So, they are contradicting each other.


Post your comments here:

Your comments will be displayed after verification.