Mechanical Engineering - Industrial Engineering and Production Management - Discussion

Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 15)
15.
In a network shown in the below figure, the critical path is along
1-2-3-4-8-9
1-2-3-5-6-7-8-9
1-2-3-4-7-8-9
1-2-5-6-7-8-9
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 2 of 4.

Abhishek said:   1 decade ago
Option B is 100% correct because it highest 24 days to complete a project and their are no effect of dummy activity for critical path.

Vetan said:   6 years ago
The critical path has the longest path and consumes maximum time and maximum resource
So option B is correct.

1-2-3-5-6-7-8-9 = 24.

S V Manikandan. said:   5 years ago
Critical path is one, which consumes more time to complete. By this way, I can choose option B. The dummy loop is unaccountable.

Vignesh reddy said:   3 years ago
@All
Option -A is correct because a dummy is said to be critical.

EST =LST.

So, there is no chance.

Karthi said:   6 years ago
The critical path consist of the longest path duration 1-2-3-5-6-7-8-9 is 24 units.

Ind Lov said:   9 years ago
The Crictical path can contain Dummy activities.

So answer B is right.

Bhavesh Shingala said:   9 years ago
Critical path does not contain dummy activities. So B is incorrect.

Vinit said:   1 decade ago
Critical path does not contain dummy activities. So B is incorrect.

Jay shankar bhatt said:   1 decade ago
Option B is not correct because we avoid looping in critical path.

Chirag Arya said:   1 decade ago
Dummy activity not considered so D is correct. It takes 22 days.


Post your comments here:

Your comments will be displayed after verification.