In a network shown in the below figure, the critical path is along


Discussion:
32 comments Page 2 of 4.
Abhishek said:
1 decade ago
Option B is 100% correct because it highest 24 days to complete a project and their are no effect of dummy activity for critical path.
Vetan said:
6 years ago
The critical path has the longest path and consumes maximum time and maximum resource
So option B is correct.
1-2-3-5-6-7-8-9 = 24.
So option B is correct.
1-2-3-5-6-7-8-9 = 24.
S V Manikandan. said:
5 years ago
Critical path is one, which consumes more time to complete. By this way, I can choose option B. The dummy loop is unaccountable.
Vignesh reddy said:
3 years ago
@All
Option -A is correct because a dummy is said to be critical.
EST =LST.
So, there is no chance.
Option -A is correct because a dummy is said to be critical.
EST =LST.
So, there is no chance.
Karthi said:
6 years ago
The critical path consist of the longest path duration 1-2-3-5-6-7-8-9 is 24 units.
Ind Lov said:
9 years ago
The Crictical path can contain Dummy activities.
So answer B is right.
So answer B is right.
Bhavesh Shingala said:
9 years ago
Critical path does not contain dummy activities. So B is incorrect.
Vinit said:
1 decade ago
Critical path does not contain dummy activities. So B is incorrect.
Jay shankar bhatt said:
1 decade ago
Option B is not correct because we avoid looping in critical path.
Chirag Arya said:
1 decade ago
Dummy activity not considered so D is correct. It takes 22 days.
Post your comments here: