15.
In a network shown in the below figure, the critical path is along
1-2-3-4-8-9
1-2-3-5-6-7-8-9
1-2-3-4-7-8-9
1-2-5-6-7-8-9
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 3 of 4.

Rash Bihari said:   10 years ago
Dummy activity should be considered. So option B is correct.

Sukarma said:   4 years ago
How to find the dummy activity? Anyone explain it.

Dhaval Chaudhary said:   6 years ago
A is correct answer 1-2-3-4-8-9.

Ref: R S Kurmi.

Bhargav said:   6 years ago
According to me, Option A is the correct answer.

Manoj said:   8 years ago
Which takes minimum time? Explain in detail.

Sonu said:   1 decade ago
What about option B which has 24+D1 days?

Jimbru said:   1 decade ago
Dummy activity will also be considered.

Neeraj said:   7 years ago
I think it is A.

Ref: RS Khurmi.

Hemant said:   1 decade ago
Why option "B" is not correct?

Vanraj Gajarotar said:   5 years ago
Option B is the right answer.