Mechanical Engineering - Industrial Engineering and Production Management - Discussion
Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 15)
15.
In a network shown in the below figure, the critical path is along


Discussion:
32 comments Page 1 of 4.
Kuldip said:
1 decade ago
Critical path is one which takes more time to complete. So 1-2-5-6-7-8-9 is taking 22 days and other path 21 day so 1256789 should be the critical path.
Sonu said:
1 decade ago
What about option B which has 24+D1 days?
Hemant said:
1 decade ago
Why option "B" is not correct?
Abhishek said:
1 decade ago
Option B is 100% correct because it highest 24 days to complete a project and their are no effect of dummy activity for critical path.
Jay shankar bhatt said:
1 decade ago
Option B is not correct because we avoid looping in critical path.
Vinit said:
1 decade ago
Critical path does not contain dummy activities. So B is incorrect.
Jimbru said:
1 decade ago
Dummy activity will also be considered.
Chirag Arya said:
1 decade ago
Dummy activity not considered so D is correct. It takes 22 days.
Rash Bihari said:
10 years ago
Dummy activity should be considered. So option B is correct.
Janardhan reddy.G said:
10 years ago
1-2-3-4-8-9 = 21.
1-2-3-5-6-7-8-9 = 24.
1-2-5-6-7-8-9 = 22.
By comparing the critical path from the above, it is concluded that option B is correct. That is critical path is given by 1-2-3-5-6-7-8-9.
Whenever if we want to know the critical path we need to consider dummy activities also for the completion of project.
1-2-3-5-6-7-8-9 = 24.
1-2-5-6-7-8-9 = 22.
By comparing the critical path from the above, it is concluded that option B is correct. That is critical path is given by 1-2-3-5-6-7-8-9.
Whenever if we want to know the critical path we need to consider dummy activities also for the completion of project.
Post your comments here: