Mechanical Engineering - Industrial Engineering and Production Management - Discussion
Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 15)
15.
In a network shown in the below figure, the critical path is along


Discussion:
32 comments Page 2 of 4.
AMAL said:
10 years ago
Option [B] is the correct answer. The dummy activities are provided to show precedence before any activity. Here it is showing that after 3 we can go to point 5.
And the critical path is the one taking the longest time in cycle. There is nothing like we cannot consider dummy in critical path. 1-2-3-5-6-7-8-9 is taking 24 units that's why it will be critical path.
And the critical path is the one taking the longest time in cycle. There is nothing like we cannot consider dummy in critical path. 1-2-3-5-6-7-8-9 is taking 24 units that's why it will be critical path.
Bhavesh Shingala said:
9 years ago
Critical path does not contain dummy activities. So B is incorrect.
Anomy said:
9 years ago
Critical path.
The sequence of stages determining the minimum time needed for an operation, especially when analyzed on a computer for a large organization.
The sequence of stages determining the minimum time needed for an operation, especially when analyzed on a computer for a large organization.
Ind Lov said:
9 years ago
The Crictical path can contain Dummy activities.
So answer B is right.
So answer B is right.
ONOSETALE said:
8 years ago
@ALL.
As an Industrial engineer, one of the function in a project is to obtain an optimal solution. However, I would suggest those against option B to study the algorithm of network diagram as regarding selecting the critical path(s).
As an Industrial engineer, one of the function in a project is to obtain an optimal solution. However, I would suggest those against option B to study the algorithm of network diagram as regarding selecting the critical path(s).
Manoj said:
8 years ago
Which takes minimum time? Explain in detail.
Kannan said:
8 years ago
Option D is the correct answer. The dummy activity doesn't consume any resource or time. So we don't consider dummy activity while choosing a critical path.
Neeraj said:
7 years ago
I think it is A.
Ref: RS Khurmi.
Ref: RS Khurmi.
Samuel said:
7 years ago
Exactly @Neeraj. But according to the definition, critical path is the longest path and consumes maximum time. So, they are contradicting each other.
Anand said:
7 years ago
CRITICAL Path:
A critical path consumes maximum resources. It is the longest path and consumes maximum time.
So the order of the network is 1-2-3-5-6-7-8-9.
Option B is correct.
A critical path consumes maximum resources. It is the longest path and consumes maximum time.
So the order of the network is 1-2-3-5-6-7-8-9.
Option B is correct.
Post your comments here: