Vignesh reddy said:
3 years ago
@All
Option -A is correct because a dummy is said to be critical.
EST =LST.
So, there is no chance.
Option -A is correct because a dummy is said to be critical.
EST =LST.
So, there is no chance.
Bhaskar said:
1 year ago
Agree, the right answer is B.