5.
If the pitch is 6 cm and rivet value is 4 tonnes, the number of rivets required for a riveted connection carrying an eccentric load of 15 tonnes at a distance of 30 cm from the centre line, is
Discussion:
19 comments Page 1 of 2.
Asif Ali said:
8 years ago
Given Data:
Pitch = p = 6cm
Rivet Value = R = 4tonnes
No.of Rivets = n = ?
Eccentric Load=P=15tonnes
Distance b/w Centre Line [ i-e Centroid (G) ] and Line of action of Eccentric Load (P) = e = 30cm.
Sol:
Formula:
n = (6M/R.p)^1/2 -------------(1).
Here,
External Moment=M=P.e/No.of Vertical Rows -------------------(2).
[I don't know why but according to the situation], The No. Of Vertical Rows = 2.
So, Now ,
Putting the values in eqn (2),
M = 15 tonnes*30cm/2.
M = 225 tonnes-cm.
Now ,
Putting all the values in eqn (1).
n=(6*225 tonnes-cm/4tonnes*6cm)^1/2.
n=(56.25)^1/2.
n=7.5.
Take it as n=8rivets.
So,
No. of Rivets=n=8 (And).
Pitch = p = 6cm
Rivet Value = R = 4tonnes
No.of Rivets = n = ?
Eccentric Load=P=15tonnes
Distance b/w Centre Line [ i-e Centroid (G) ] and Line of action of Eccentric Load (P) = e = 30cm.
Sol:
Formula:
n = (6M/R.p)^1/2 -------------(1).
Here,
External Moment=M=P.e/No.of Vertical Rows -------------------(2).
[I don't know why but according to the situation], The No. Of Vertical Rows = 2.
So, Now ,
Putting the values in eqn (2),
M = 15 tonnes*30cm/2.
M = 225 tonnes-cm.
Now ,
Putting all the values in eqn (1).
n=(6*225 tonnes-cm/4tonnes*6cm)^1/2.
n=(56.25)^1/2.
n=7.5.
Take it as n=8rivets.
So,
No. of Rivets=n=8 (And).
(11)
Pramit Samanta said:
4 years ago
The number of rivet lines is not provided. Then how to predict?
(3)
Balkaran Sidhu said:
1 decade ago
After calculating rivet value,
No.of rivets = total load/ rivet Value.
No.of rivets = total load/ rivet Value.
(1)
Vina said:
4 years ago
N = (6m/rv)^.5.
(1)
Sejal said:
8 years ago
What is the value of s?
(1)
Deepanshu said:
1 decade ago
(6M/lpR)^1/2.
(6x30x15/2x6x4)^1/2.
7.5 answer.
8 rivet.
(6x30x15/2x6x4)^1/2.
7.5 answer.
8 rivet.
(1)
Soumyadip said:
1 decade ago
From which formula I can determine the strength of rivet? Please help me. Thank you.
Gurpreet Singh said:
1 decade ago
The simple method to find no. of rivet is-it is the question of bracket connection so in this connection same no. of rivets are required on each flange to connect the bracket.
So each side required. Rivets are = 15/4 = 3.75 = 4 rivets each side, so total no. of rivets required both side for connection are = 8.
So each side required. Rivets are = 15/4 = 3.75 = 4 rivets each side, so total no. of rivets required both side for connection are = 8.
Agni said:
9 years ago
What is the formula for strength in shearing and bearing?
Saurabh pal said:
9 years ago
According to me,
Mri/(nri2) + p.
n = 15
Mri/(nri2) + p.
n = 15
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers