For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
0.200 m3
0.247 m3
0.274 m3
0.295 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
43 comments Page 3 of 5.

Deepak said:   7 years ago
Why to increase by its 30%?

Naveen Srivastava said:   7 years ago
0.278 is the incorrect answer.

There is no need to add an extra 25%.
It's Converted to wet volume to dry volume by 1.30.
The Correct ans is 100 * 0.012 * 1.30 = 1.56 * (1/7) = 0.222cum.

Sachin das said:   7 years ago
For 1 m3,
Dry volume = 1m3,
Wet volume is 35% of dry volume,
So we have to take.

1: 6 = 1.35 ( 1.35 m3 become 1m3 after adding water in mortor....and for concrete we take 55%....1.54m3 = 1m3).
1+ 6 = 7........1.35/7 = 0.193 cement required per m3,
Volume = 12/1000 * 100 = 1.2 m3,
Required cement volume= 1.2 * 0.193 =0.23.

Muthu nayak said:   7 years ago
dry vol=area*thckness*1.3*1.25.
dry vol=100*0.012*1.3*1.25.
=1.95cum,

Cement=1.95/1+6,
Cement=0.278cum,

Mohit Motwani said:   8 years ago
Volume of mortar required= 100*.12 = 1.2.
Total 60% of volume increases for dry mortar
1.2+ (.60* 1.2)= 1.92.

Now volume of cement = 1/7 * 1.92= 0.2743.

Adhiyaman said:   8 years ago
Thanks to all.

Salma said:   8 years ago
1*100*. 012*1. 54/7 =. 274.

Mohit said:   8 years ago
If it is 15 mm thick than answer is .345 cum.

Shahanshah khan said:   8 years ago
I think dry value taken so large in solution maximum take extra 20% to 30%.

Sufazo said:   8 years ago
According to this answer, they taking 60% extra => 1.2 * 60/100 = 0.274.