8.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
500 m3
1000 m3
1500 m3
2000 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
42 comments Page 2 of 5.

Akash Singh said:   5 years ago
Original volume= 1000*8*(15+10) = 2000m3.
Cut off volume= 1/4 * 2000 = 500m3.
Box cutting=2000-500= 1500m3.
(1)

Vikas kumar said:   8 years ago
2000 Cum is the correct answer.
(1)

Deeptikant sharma said:   8 years ago
15/4 = 3.75 then,

10cm - compaction 3.75 = 6.25 cm.
(1)

Burhan said:   8 years ago
@Rishabh.

Why you divide 2000 by 4?

Bharath said:   8 years ago
6.25 cm fixed ah?

Vinod said:   7 years ago
What is 6.25?

Bipin said:   7 years ago
Box cutting in road crust= 1000 * 8 * (0.15+0.10).
= 2000m^3.

Sonali said:   7 years ago
I think the answer is 2000m3 is correct.

Navjot said:   7 years ago
Original volume= as you know = 2000.

Cutt off volume= 1/4 of the original volume.
1/4x2000 = 500cum.
So, box cutting in road = 2000 - 500 = 1500 cum.

Sumit said:   7 years ago
How 6.25 cm?