Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 2 (Q.No. 17)
17.
The expected out turn of half brick partition wall per mason per day is
Discussion:
50 comments Page 1 of 5.
Abdul latif said:
4 years ago
The answer should be in sq.m for half brick ,because half brick quantity is calculated in sq.m or sq.ft not in cu.m or cu.ft ,so option D looks correct answer.
Ref: R.Agour.
Ref: R.Agour.
Dr. Buch said:
3 years ago
Substructure: 1.25m3.
Superstructure: 1.00m3.
Mud mortar: 1.5 and 1.25 m3.
Arches: 55 m3.
Half brick: 5 m2.
RCC: 3 m3.
RB: 1 m3.
12mm plastering 8 m2.
Superstructure: 1.00m3.
Mud mortar: 1.5 and 1.25 m3.
Arches: 55 m3.
Half brick: 5 m2.
RCC: 3 m3.
RB: 1 m3.
12mm plastering 8 m2.
(2)
Yadav said:
4 years ago
Substructure 1.25m3.
Superstructure 1.00m3.
Mud mortar - 1.5 and 1.25 m3.
Arches .55 m3.
Half brick 5 m2.
RCC 3 m3.
RB 1 m3.
12mm plastering 8 m2.
Superstructure 1.00m3.
Mud mortar - 1.5 and 1.25 m3.
Arches .55 m3.
Half brick 5 m2.
RCC 3 m3.
RB 1 m3.
12mm plastering 8 m2.
(1)
Baloch said:
4 years ago
Halfbrick work is Calculated in Squire meter. the value of option B is in cubic meter.
So, the answer is option D.
Reference R.Agor.
So, the answer is option D.
Reference R.Agor.
Alpesh mali said:
3 years ago
D is right.
Substructure: 1.25m^3.
Superstructure: 1.00m^3.
Mud mortar: 1.5 and 1.25 m^3.
Arches: 55 m^3.
Half brick: 5 m^2.
Substructure: 1.25m^3.
Superstructure: 1.00m^3.
Mud mortar: 1.5 and 1.25 m^3.
Arches: 55 m^3.
Half brick: 5 m^2.
(1)
Azar mujawar said:
6 years ago
It's 5 for half-brick.
Rcc work - 3.25.
Distemper - 35.
Excavation of soil - 3.
Concrete - 5.
12 mm plaster - 8.
Rcc work - 3.25.
Distemper - 35.
Excavation of soil - 3.
Concrete - 5.
12 mm plaster - 8.
Ankur Jain said:
8 years ago
Yes, D is correct answer.
Half brick wall in the partition - 5.00 sq m, Quantity Per Day = 50.00 cu ft.
Half brick wall in the partition - 5.00 sq m, Quantity Per Day = 50.00 cu ft.
Yuvi said:
6 years ago
Mason work per day concrete work = 5 m^3.
Earth excavation or earthwork = 3 m^3.
Brick work = 2 m^3.
Earth excavation or earthwork = 3 m^3.
Brick work = 2 m^3.
Karmvir Yadav said:
1 decade ago
Answer D is correct because half brick work is measured in square meter not in m3.
Abhishek Kumar said:
7 years ago
The Correct Answer is 5 sq metre.
Ref: B.N.Dutta Estimating and Costing.
Ref: B.N.Dutta Estimating and Costing.
Post your comments here: