Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 2 (Q.No. 17)
17.
The expected out turn of half brick partition wall per mason per day is
Discussion:
50 comments Page 1 of 5.
Bashishth Baitha said:
2 years ago
I think the correct answer is option D.
(1)
Uttam Khanra said:
2 years ago
First, Half bricks partition wall will be in m2. It will be 7.5m2.
James said:
2 years ago
I think the correct answer, is option (d).
Alpesh mali said:
3 years ago
D is right.
Substructure: 1.25m^3.
Superstructure: 1.00m^3.
Mud mortar: 1.5 and 1.25 m^3.
Arches: 55 m^3.
Half brick: 5 m^2.
Substructure: 1.25m^3.
Superstructure: 1.00m^3.
Mud mortar: 1.5 and 1.25 m^3.
Arches: 55 m^3.
Half brick: 5 m^2.
(1)
Dr. Buch said:
3 years ago
Substructure: 1.25m3.
Superstructure: 1.00m3.
Mud mortar: 1.5 and 1.25 m3.
Arches: 55 m3.
Half brick: 5 m2.
RCC: 3 m3.
RB: 1 m3.
12mm plastering 8 m2.
Superstructure: 1.00m3.
Mud mortar: 1.5 and 1.25 m3.
Arches: 55 m3.
Half brick: 5 m2.
RCC: 3 m3.
RB: 1 m3.
12mm plastering 8 m2.
(2)
Narendra said:
3 years ago
Half brick work is in sq.m.
Engr khan said:
3 years ago
Option D. 5 m^2 is the correct answer.
(1)
Jagat Khadka said:
3 years ago
5m^2 is the Correct Answer.
Aman said:
4 years ago
5m2 is the correct answer.
Yadav said:
4 years ago
Substructure 1.25m3.
Superstructure 1.00m3.
Mud mortar - 1.5 and 1.25 m3.
Arches .55 m3.
Half brick 5 m2.
RCC 3 m3.
RB 1 m3.
12mm plastering 8 m2.
Superstructure 1.00m3.
Mud mortar - 1.5 and 1.25 m3.
Arches .55 m3.
Half brick 5 m2.
RCC 3 m3.
RB 1 m3.
12mm plastering 8 m2.
(1)