Pick up the correct statement from the following:

A. Pointing is measured in sq.m
B. Plastering is measured in sq.m
C. Glazing is measured in sq.m
D. Striking is measured in sq.m
E. All the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

17. 

The expected out turn of half brick partition wall per mason per day is

A. 1.5 m3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

18. 

If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is

A. B + d + Sd
B. Bd + Sd2
C. B x d - Sd1/2
D. (Bd + Sd2)

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

19. 

The floor area includes the area of the balcony up to

A. 100%
B. 75%
C. 50%
D. 25%

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

20. 

The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is

A.
B.
C.
D.

Answer: Option A

Explanation: