The expected out turn of half brick partition wall per mason per day is
1.5 m3
2.0 m3
4.0 m2
5.0 m2
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
51 comments Page 2 of 6.

Yadav said:   4 years ago
Substructure 1.25m3.
Superstructure 1.00m3.
Mud mortar - 1.5 and 1.25 m3.
Arches .55 m3.
Half brick 5 m2.
RCC 3 m3.
RB 1 m3.
12mm plastering 8 m2.
(1)

Baloch said:   4 years ago
Halfbrick work is Calculated in Squire meter. the value of option B is in cubic meter.


So, the answer is option D.

Reference R.Agor.

Syed mehak Qadri said:   4 years ago
Option D. 5m^2 is the correct answer.

MD SAIF said:   4 years ago
D) 5 meter square is the right answer.

Madhusmita sahu said:   4 years ago
Agree, D is the correct answer.

Sanjay said:   4 years ago
5sqm is correct.

Abdul latif said:   4 years ago
The answer should be in sq.m for half brick ,because half brick quantity is calculated in sq.m or sq.ft not in cu.m or cu.ft ,so option D looks correct answer.

Ref: R.Agour.

Shahid said:   4 years ago
5 * 0.115 = 0.575cum.

Rinhlua said:   5 years ago
The correct answer is D.

Shrutigupta said:   5 years ago
The right answer is D.